ICRR 10426 Report Number : ICRR10426 ICR Review Operations Evaluation Department 1. Project Data : OEDID: OEDID : C2109 Project ID : P000925 Project Name : Sixth Power Country : Ghana Sector : Electric Power & Other Energy Adjustment L/C Number : Credit 2109-GH Partners involved : EIB, CCCE, AFDB, SIDA Prepared by : Sunil Mathrani, OEDST Reviewed by : Alain A. Barbu Group Manager : Gregory K. Ingram Date Posted : 08/26/1999 2. Project Objectives, Financing, Costs and Components : The project, supported by a Credit of SDR 15.2 million, (US$20 million) was approved in FY90 and closed in FY98, two years later than scheduled . Only 28% of the Credit was disbursed and a total of SDR 10.9 million was canceled because only one of the project's physical components was fully completed . The stated objectives of the project were to assist the implementing agency, The Volta River Authority (VRA) to (a) maintain the high standard of reliability of the country's electricity supply; (b) meet projected domestic and export demand through 1995, including an interconnection with Burkina Faso; and (c) implement its ongoing program of institutional development . The project comprised (i) the rehabilitation of the Akosombo hydro power plant, (ii) construction of transmission lines in north-western Ghana and an interconnection with Burkina Faso, (iii) construction of a bulk power supply substation in Accra, (iv) distribution materials for network extension in northern Ghana, (v) construction of a training center, and (vi) studies for future generation and transmission needs and tariff policies . 3. Achievement of Relevant Objectives : The project failed to meet virtually all of its objectives . The original technical solution for the rehabilitation of the Akosombo plant was abandoned after the first refurbished unit failed to deliver the expected efficiency gain . It was therefore decided to replace the turbine runners instead of refurbishing them . IDA financed the design and model testing of the new runners. These will provide higher efficiencies than those envisaged at project appraisal . The replacement will cost about US$120 million instead of US$64 million for refurbishment. The work will be completed in 2004 with financing from EIB and VRA itself. Only one of the transmission lines has been fully completed . Work on the line to Burkina Faso and the training school has yet to commence . 4. Significant Achievements : None. 5. Significant Shortcomings : The project was poorly designed and appraised . As pointed out by the ICR, the possibility of exceeding the original 40-year old turbine efficiency by redesigning the runners should have been examined from the outset . No understanding on power tariffs had been reached with Burkina Faso prior to Board approval . The project was inadequately supervised and should have been restructured at an early stage . GOG seriously weakened VRA's ability to meet its local cost obligations by failing to authorize timely tariff increases . 6. Ratings : ICR OED Review Reason for Disagreement /Comments Outcome : Unsatisfactory Unsatisfactory Institutional Dev .: Negligible Negligible Sustainability : Uncertain Uncertain Bank Performance : Satisfactory Unsatisfactory Serious shortcomings in preparation, appraisal, and supervision are highlighted in the text of the ICR (see Section 9 below) Borrower Perf .: Deficient Unsatisfactory Quality of ICR : Satisfactory 7. Lessons of Broad Applicability : (a) Thorough design and preparation prior to appraisal are essential to avoid serious implementation problems; (b) Agreements on contractual terms and tariffs should precede projects to finance international power trade; and (c) Political interference in tariff setting can seriously undermine the finances of even the strongest power utilities in a very short time span. 8. Audit Recommended? Yes No Why? Possibly in the context of a broader review of the Bank's assistance to Ghana's Energy Sector . 9. Comments on Quality of ICR : The ICR is of generally good quality and objective in its discussion of the project's shortcomings . The computation of the EIRR for the turbine replacement is inappropriate given that this component has yet to be implemented . This review only disagrees with the satisfactory rating for overall Bank performance, which is inconsistent with the ICR ’s own assessment of the Bank's performance during preparation and supervision .
Groupe de la Banque mondiale · Implementation Completion Report Review
Ghana - Sixth Power
Voir le document original
Le texte intégral est hébergé par l’organisation qui le publie. lawenc.com indexe les métadonnées et renvoie vers la source officielle.
Texte intégral
Informations clés
Organisation
Groupe de la Banque mondiale
Type de document
Implementation Completion Report Review
Pays
Ghana
Source
Banque mondiale