Page 1 No Activity / Description Source of Financing Procure- ment Method Prior / Post Review Status RFP / TOR ready WB non- objection SPN / REOI Deadline expres- sion of interest Shortlist approved by CNP WB non- objection RFP sent to consul- tant(s) / invitation Deadline proposal submiss-ion/ interview (IC) Name of Supplier / Contractor / Consultant 1 2 3 4 5 6 7 8 9 11 12 13 14 15 16 plan 1-Apr-10 15-Apr-10 20-Apr-10 4-May-10 18-May-10 1-Jun-10 6-Jun-10 6-Jul-10 revised n/a n/a n/a n/a n/a n/a n/a n/a actual 15-Mar-09 6-Apr-09 12-Feb-10 1-Mar-10 22-Apr-10 26-May-10 19-Jul-10 30-Aug-10 plan 12-Mar-10 26-Mar-10 31-Mar-10 10-Apr-10 24-Apr-10 8-May-10 13-May-10 23-May-10 revised n/a n/a n/a n/a n/a n/a n/a n/a actual 17-Nov-09 ######## n/a n/a 22-Dec-09 14-Jan-10 15-Jan-10 25-Jan-10 plan 5-Jun-10 19-Jun-10 24-Jun-10 4-Jul-10 8-Jul-10 22-Jul-10 27-Jul-10 10-Aug-10 revised n/a n/a n/a n/a n/a n/a n/a n/a actual 29-Jun-10 14-Jul-10 27-Jul-10 4-Aug-10 10-Mar-11 29-Mar-11 31-Mar-11 11-Apr-11 plan 3-Apr-10 17-Apr-10 22-Apr-10 6-May-10 20-May-10 3-Jun-10 8-Jun-10 8-Jul-10 revised 15-Mar-11 25-Mar-11 28-Mar-11 11-Apr-11 18-Apr-11 28-Apr-11 1-May-11 15-May-11 actual 29-Mar-11 plan 28-Jun-10 12-Jul-10 17-Jul-10 27-Jul-10 10-Aug-10 24-Aug-10 29-Aug-10 8-Sep-10 revised n/a n/a n/a n/a n/a n/a n/a n/a actual 29-Jun-10 14-Jul-10 26-Jul-10 4-Aug-10 14-Nov-10 17-Dec-10 15-Jan-11 18-Jan-11 repeat n/a n/a 11/03/11 21/03/11 01/04/11 plan n/a n/a n/a n/a n/a n/a n/a n/a revised 1-Oct-10 15-Oct-10 20-Oct-10 30-Oct-10 9-Nov-10 23-Nov-10 28-Nov-10 8-Dec-10 actual 06/12/10 15/12/10 28/12/10 15/01/11 17/02/11 plan n/a n/a n/a n/a n/a n/a n/a n/a revised n/a n/a n/a n/a n/a n/a n/a n/a actual 14-Dec-10 13-Jan-11 n/a n/a n/a n/a n/a n/a Mr. Francisco Ayala CQ 2 International Individual Consultant for Conditional Cash Transfer 7 5 TF095274 COMMUNITY NUTRITION PROJECT (WB FINANCED) 3 Local Accounting/Financial Firm 1 National Individual Financial Consultant to LWU and DHP 4 Consulting firm for Community Based Nutrition TF095274/ TF097071 TF095274 SS TF095274 TF095274 TF095274 prior International Procurement Advisor (part-time) prior CNP PROCUREMENT PLAN: March 2011 Bank NoL Oct 5, 10 External Audit Firm Senior Project Administrator CONSULTANTS: prior Mr. Marian Nenita TF095274 IC prior LCS prior QBS IC post 6 IC post
Groupe de la Banque mondiale · Procurement Plan
Lao People's Democratic Republic - Community Nutrition Project : procurement plan
Voir le document original
Le texte intégral est hébergé par l’organisation qui le publie. lawenc.com indexe les métadonnées et renvoie vers la source officielle.
Texte intégral
Informations clés
Organisation
Groupe de la Banque mondiale
Type de document
Procurement Plan
Source
Banque mondiale