Page 1 Iran- P076884- Northern Cities Water & Sanitation Procurement Plan as of October 31, 2010 Selection of Consultants Rasht Supervision P QCBS PRIOR 02-Jan-06 56 27-Feb-06 31-Jan-06 28-Feb-06 14 14-Mar-06 7 21-Mar-06 28 18-Apr-06 28 16-May-06 10 26-May-06 7 02-Jun-06 28 30-Jun-06 14 14-Jul-06 30 13-Aug-06 14 27-Aug-06 14 10-Sep-06 14 24-Sep-06 Supervision R QCBS PRIOR 26-Feb-06 56 04-Aug-06 04-Aug-06 11-Aug-06 14 25-Aug-06 7 01-Sep-06 29 30-Sep-06 29 29-Oct-06 11 09-Nov-06 8 17-Nov-06 29 16-Dec-06 15 31-Dec-06 31 31-Jan-07 15 15-Feb-07 15 02-Mar-07 15 17-Mar-07 Supervision A QCBS PRIOR 26-Feb-06 261 13-Nov-06 29-Oct-06 14-Nov-06 8 22-Nov-06 6 28-Nov-06 84 18-Feb-07 113 10-Jun-07 2 12-Jun-07 18 30-jun-o7 9 09-Jul-07 1 10-Jul-07 11 21-Jul-07 61 39349 7 39356 0 39356 IranAb/]Iran Anzali Supervision P QCBS Yes 02-Jan-06 56 27-Feb-06 31-Jan-06 28-Feb-06 14 14-Mar-06 7 21-Mar-06 28 18-Apr-06 28 16-May-06 10 26-May-06 7 02-Jun-06 28 30-Jun-06 14 14-Jul-06 30 13-Aug-06 14 27-Aug-06 14 10-Sep-06 14 24-Sep-06 Supervision R QCBS Yes 26-Feb-06 56 04-Aug-06 04-Aug-06 11-Aug-06 14 25-Aug-06 7 01-Sep-06 29 30-Sep-06 29 29-Oct-06 11 09-Nov-06 8 17-Nov-06 29 16-Dec-06 15 31-Dec-06 31 31-Jan-07 15 15-Feb-07 15 02-Mar-07 15 17-Mar-07 Supervision A QCBS Yes 26-Feb-06 261 14-Nov 30-Oct-06 15-Nov-06 7 22-Nov-06 6 28-Nov-06 80 14-Feb-07 130 23-Jun-07 0 23-Jun-07 10 03-Jul-07 35 07-Aug-07 2 09-Aug-07 7 15-Aug-07 72 26-sep-o7 4 39355 7 39362 SNC Lavlin/ Canada Rasht &Anzali Environmental Studies for Rash & Anzali P QCBS Post 02-Jun-06 84 24-Aug-06 24-Aug-06 15-Sep-06 15 30-Sep-06 10 10-Oct-06 25 05-Nov-06 25 30-Nov-06 15 15-Dec-06 15 15-jan--07 20 5-Feb--07 10 15-Feb-07 30 15-Mar-07 10 25-Feb-07 20 15-Apr-07 20 05-May-07 Name of consultant Time Interval Time Interval Bank N.O. Signing of Contrct Time Interval B ank N.O., Draft Contrct Issue of RFP Time Interval Time Interval Time Interval Time Interval Time Interval Start of Assignment Final Evaluation R eport Bank N.O. Negotation of C ontract T ime Interval Time Interval Opening of financial Proposals Time Interval Preparation of Shortlist Time Interval Ref.No. Time Interval plan-revised - actual Description Review By Bank (PRIOR /Post) Selection Method Requested for EOI Advertisement Prepatiion of RFP Time Interval Preparation of TOR Submission of Proposal Tech. Evaluation Bank N.O. GTA-1 GTA-2 GTA-3 Preparation of Environmental Monitoring Program (EMP) R QCBS Post 10-Jun-07 49 29-Jul-07 29-Jul-07 6 05-Aug-07 7 12-Aug-07 7 19-Aug-07 28 16-Sep-07 28 13-Oct-07 7 20-Oct-07 7 27-Oct-07 7 02-Nov-07 7 09-Nov-07 7 16-Nov-07 7 22-Nov-07 14 06-Dec-07 14 20-Dec-07 Preparation of Environmental Monitoring Program (EMP) A QCBS Post 09-Sep-07 100 39434 01-Jan-08 4 39452 39457 28 06-Feb-08 72 28-Apr-08 11-May-08 1 39580 25 39605 3 09-Jun-08 19 28-Jun-08 Pajoohesh Kade Mohitzist Jahad Environmental Studies for Rash & Anzali P QCBS Post 02-Jun-06 84 24-Aug-06 24-Aug-06 21 15-Sep-06 15 30-Sep-06 10 10-Oct-06 25 05-Nov-06 25 30-Nov-06 15 15-Dec-06 15 15-jan--07 20 5-Feb--07 10 15-Feb-07 30 15-Mar-07 10 25-Feb-07 20 15-Apr-07 20 05-May-07 R QCBS Post 10-Jun-07 49 29-Jul-07 29-Jul-07 6 05-Aug-07 7 12-Aug-07 7 19-Aug-07 28 16-Sep-07 28 13-Oct-07 7 20-Oct-07 7 27-Oct-07 7 02-Nov-07 7 09-Nov-07 7 16-Nov-07 7 22-Nov-07 14 06-Dec-07 14 20-Dec-07 A QCBS Post 19-Sep-09 60 21-Nov-09 1 40139 38 30-Oct-09 2 40149 46 40196 18-Jan-10 108 06-May-10 20-May-10 26 14-Jun-10 14-Jun-10 54 07-Sep-10 Toosab Consultant Rasht &Anzali Environmental Studies for Rash & Anzali P QCBS Post 02-Jun-06 84 24-Aug-06 24-Aug-06 21 15-Sep-06 15 30-Sep-06 10 10-Oct-06 25 05-Nov-06 25 30-Nov-06 15 15-Dec-06 15 15-jan--07 2 5-Feb--07 10 15-Feb-07 30 15-Mar-07 10 25-Feb-07 20 15-Apr-07 20 05-May-07 Preparation of Emergency Operational Plan (EOP) R QCBS Post 10-Jun-07 49 29-Jul-07 29-Jul-07 6 05-Aug-07 7 12-Aug-07 7 19-Aug-07 28 16-Sep-07 28 13-Oct-07 7 20-Oct-07 7 27-Oct-07 7 02-Nov-07 7 09-Nov-07 7 16-Nov-07 7 22-Nov-07 14 06-Dec-07 14 20-Dec-07 Preparation of Emergency Operational Plan (EOP) A QCBS Post 09-Sep-07 100 39434 39448 4 39452 82 39544 32 39574 19-Jun-08 13 02-Aug-08 12-Aug-08 0 12-Aug-08 16 28-Aug-08 9 07-Sep-08 43 20-Oct-08 1 21-Oct-08 Parsab Tadbir Co/Iran Rasht &Anzali Environmental Studies for Rash & Anzali P QCBS Post 02-Jun-06 84 24-Aug-06 24-Aug-06 21 15-Sep-06 15 30-Sep-06 10 10-Oct-06 25 05-Nov-06 25 30-Nov-06 15 15-Dec-06 15 15-jan--07 20 5-Feb--07 10 15-Feb-07 30 15-Mar-07 10 25-Feb-07 20 15-Apr-07 20 05-May-07 Health Related Study (Baseline Environmental Data) R QCBS Post 10-Jun-07 49 29-Jul-07 29-Jul-07 6 05-Aug-07 7 12-Aug-07 7 19-Aug-07 28 16-Sep-07 28 13-Oct-07 7 20-Oct-07 7 27-Oct-07 7 02-Nov-07 7 09-Nov-07 7 16-Nov-07 7 22-Nov-07 14 14 20-Dec-07 Health Related Study (Baseline Environmental Data) A IC Post 02-Jun-09 15 20-Jun-09 13-Jan-09 265 15 20-Sep-09 05-Sep-09 19-Sep-09 19-Sep-09 22 11-Oct-09 Mr Kolahi Rasht &Anzali Environmental Studies for Rash & Anzali P QCBS Post 02-Jun-06 84 24-Aug-06 24-Aug-06 21 15-Sep-06 15 30-Sep-06 10 10-Oct-06 25 05-Nov-06 25 30-Nov-06 15 15-Dec-06 15 15-jan--07 20 5-Feb--07 10 15-Feb-07 30 15-Mar-07 10 25-Feb-07 20 15-Apr-07 20 05-May-07 Consulting service for the Septage Study for Rasht and Anzali R QCBS Post 10-Jun-07 49 29-Jul-07 29-Jul-07 6 05-Aug-07 7 12-Aug-07 7 19-Aug-07 28 16-Sep-07 28 13-Oct-07 7 20-Oct-07 7 27-Oct-07 7 02-Nov-07 7 09-Nov-07 7 16-Nov-07 7 22-Nov-07 14 06-Dec-07 14 20-Dec-07 Consulting service for the Septage Study for Rasht and Anzali A QCBS Post 09-Sep-07 100 39434 39448 9 39457 21 39478 34 39546 61 39608 16-Jun-08 75 18-Aug-08 1 19-Aug-08 30 28-Sep-08 20-Oct-08 18 08-Nov-08 Taghigat Pishrateh co/ Iran Rasht &Anzali Environmental Studies for Rash & Anzali P QCBS Post 02-Jun-06 84 24-Aug-06 24-Aug-06 21 15-Sep-06 15 30-Sep-06 10 10-Oct-06 25 05-Nov-06 25 30-Nov-06 15 15-Dec-06 15 15-jan--07 20 5-Feb--07 10 15-Feb-07 30 15-Mar-07 10 25-Feb-07 20 15-Apr-07 20 05-May-07 Consulting service for the Sludge Staudy R QCBS Post 10-Jun-07 49 29-Jul-07 29-Jul-07 6 05-Aug-07 7 12-Aug-07 7 19-Aug-07 28 16-Sep-07 28 13-Oct-07 7 20-Oct-07 7 27-Oct-07 7 02-Nov-07 7 09-Nov-07 7 16-Nov-07 7 22-Nov-07 14 06-Dec-07 14 20-Dec-07 Consulting service for the Sludge Staudy A IC Post 02-Jun-09 18 39984 40057 40066 40071 10-Sep-09 14-Sep-09 23-Sep-09 Dr. Farkhoki (Engineer Officer) A IC PRIOR 23-Sep-06 23-Sep-06 Sep-23-06 Mr.Eildar Dadvar (Procurement Officer) A IC PRIOR 23-Sep-06 23-Sep-06 Sep-23-06 Jahanshah Aliyan Financial A IC PRIOR 11-Nov-06 12-Nov-06 12-Nov-06 Hossin Mansor (Enviormental) A IC PRIOR 02-Sep-05 23-Oct-05 23-Oct-05 Hossin Ganjidost Financial A IC PRIOR 21-Nov-07 25-Oct-07 25-Oct-07 Hassan Haydari (Procurement Officer) A IC PRIOR 02-Sep-05 23-Oct-05 23-Oct-05 Hissin Eslami Financial A IC PRIOR 02-Sep-05 23-Oct-05 23-Oct-05 Shaer Biyaban (Enviormental) IC PRIOR 15-Apr-09 Frarideh Gholami (1) Based on the World Bank no objection, it was agreed t o appoint the individual GTA-5 GTA-6(1) GTA-3 GTA-4 GTA-7 GTA-8(1) Based on the world bank NO for selection of consultant for environmental studies Rash & Anzali has been modified to 6 above mentioned consultant the Industrial Waste Compliance Action Plans (CAPs) P= Planned R= Revised A= Actual Page 2 Remark The contract has been terminate by IC dated Mar 20,2009 The contract has been terminate The contract has been terminate The contract has been terminate The contract has been terminate The contract has been terminate P= Planned R= Revised A= Actual Page 3 Iran- P076884- Northern Cities Water & Sanitation Procurement Plan as of October 31, 2010 Sl. # Tender Number Package Name/ Contract ID. No. Plan /Revised/Actu Procurement Method Review By Bank (PRIOR Submission/ Readiness Date Interval /d WB No Objection Date Interval /d Invitation Date Interval /d Expected Bid-Opening Date Interval /d Evaluation & Recomm. Interval /d WB No Objection Date Interval /d Contract F inalisation Interval /d WB No O bjection Date I nterval /d Contract S ignature Date I nterval /d Start Date E xecution /b Progress (%) Disburesment with a djusment & Disburesment w ith out adjusment & Completion D ate I nterval /d Comple t ion Date A B C E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF P NCB POST R NCB POST 01-May-10 7 15-May-10 35 19-Jun-10 21 10-Jul-10 21 31-Jul-10 14 14-Aug-10 14 28-Aug-10 90 26-Nov-10 P NCB POST 7 30 30 15 30 539 R NCB POST 01-May-10 7 15-May-10 35 19-Jun-10 21 10-Jul-10 21 31-Jul-10 14 14-Aug-10 14 28-Aug-10 90 26-Nov-10 A NCB POST 15-May-10 17 02-Jun-10 19 21-Jun-10 37 28-Jul-10 22 28-Sep-10 2 30-Sep-10 P NCB POST 7 31 30 15 30 719 R NCB POST 01-May-10 7 15-May-10 35 19-Jun-10 21 10-Jul-10 21 31-Jul-10 14 14-Aug-10 14 28-Aug-10 90 26-Nov-10 A NCB POST 15-May-10 17 02-Jun-10 19 21-Jun-10 37 28-Jul-10 19 161 68 141 609 P NCB POST 7 30 30 21 15 30 539 R NCB POST 01-May-10 7 15-May-10 35 19-Jun-10 21 10-Jul-10 21 31-Jul-10 14 14-Aug-10 14 28-Aug-10 90 26-Nov-10 A NCB POST 15-May-10 17 02-Jun-10 19 21-Jun-10 37 28-Jul-10 30 28 194 132 609 P NCB POST 7 30 29 15 30 360 F R Shopping Prior 15-Sep-10 7 23-Sep-10 7 30-Sep-10 14 14-Oct-10 7 21-Oct-10 7 28-Oct-10 14 11-Nov-10 7 18-Nov-10 7 25-Nov-10 21 16-Dec-10 A 1) Any bid no received in bid opening stage (1) The prequalification of this package will be conducted prior to completion of the Bidding Document. * Sum of Actal Cost /estimated Cost F- First Year Implementation packages Exchange rate: US$ 1= IRR 9200 P ermiseble delyes Goods RG9 Operation & Maintenance and inspection Equipments(camera) A NCB POST 15-May-10 22 25-May-10 26 jun-21-10 37 28-Jul-10 35 02-Sep-10 18 20-Sep-10 RG12 Laboratories Equipment (General equipment and Spectrophotometer 609 16 48 RG10 Laboratories Equipment (HLPC and TOC Analyzer) RG11 Laboratories Equipment (Microscope and camera) the plan dated of preliminary procurment plan has been written one year before the loan effectiveness dated (Oct25 05) and we did not started the works . The principle of permiseble RG13 Laboratories EquiLaboratories Equipment (Computer Hardware and UPS) Page 4 Comments (Contractor's Name & cuntry ) AG Page 5 Iran- P076884- Northern Cities Water & Sanitation Rasht Procurement Plan as of October 31, 2010 Sl. # Tender Number Package Name/ Contract ID. No. plan-revised - actual Procurement Method Review By Bank (PRIOR /Post) Submission/ Readiness Date Interval /d WB No Objection Date Interval /d Invitation Date Interval /d Expected Bid-Opening Date Interval /d Evaluation & Recomm. Interval /d WB No Objection Date Interval /d Contract Finalisation Interval /d WB No Objection Date Interval /d Contract Signature Date Interval /d Start Date Execution /d Progress (%) D isbursement with out a djusment & Advance Disbursement with adjusment & Advance Completion Date A B C E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF Int erv al /d Ne w Co mp l eti 1-Extension A5,A6,A7,A8 P ICB PRIOR 30-Sep-05 21 21-Oct-05 7 28-Oct-05 29 27-Nov-05 30 27-Dec-05 21 17-Jan-06 15 01-Feb-06 30 03-Mar-06 1050 15-Feb-09 R ICB PRIOR 05-Jan-08 14 19-Jan-08 14 01-Feb-08 42 14-Mar-08 14 28-Mar-08 7 04-Apr-08 14 18-Apr-08 14 02-May-08 21 23-May-08 7 30-May-08 600 30-Sep-09 ZA5 A ICB PRIOR 05-Jan-08 61 05-Mar-08 10 15-Mar-08 37 21-Apr-08 142 09-Sep-08 28 07-Oct-08 20 27-Oct-08 28-Nov-08 12 08-Dec-08 730 48.07 40.28 53.00 08-Dec-10 ZA6 A ICB PRIOR 05-Jan-08 61 05-Mar-08 10 15-Mar-08 37 21-Apr-08 142 09-Sep-08 28 07-Oct-08 20 27-Oct-08 28-Nov-08 90 26-Jan-09 730 68.23 63.06 67.00 26-Jan-11 ZA7 A ICB PRIOR 05-Jan-08 61 05-Mar-08 10 15-Mar-08 37 21-Apr-08 142 09-Sep-08 28 07-Oct-08 24 02-Nov-08 12-Dec-08 70 17-Feb-09 485 73.60 60.63 62.00 17-May-10 ZA8 A ICB PRIOR 05-Jan-08 61 05-Mar-08 10 15-Mar-08 37 21-Apr-08 142 09-Sep-08 28 07-Oct-08 20 27-Oct-08 41 07-Dec-08 140 27-Apr-09 730 47.92 36.84 49.00 27-Apr-11 P ICB PRIOR 01-Jan-05 21 22-Jan-05 7 29-Jan-05 30 28-Feb-05 27 28-Mar-05 51 18-May-05 28 15-Jun-05 14 29-Jun-05 35 03-Aug-05 28 31-Aug-05 609 04-Mar-07 R ICB PRIOR 31-May-06 14 14-Jun-06 14 28-Jun-06 49 02-Sep-06 35 07-Oct-06 14 21-Oct-06 28 18-Nov-06 14 02-Dec-06 35 06-Jan-07 28 03-Feb-07 609 4-ct-08 A ICB PRIOR 20-May-06 41 30-Jun-06 15 15-Jul-06 36 31-Aug-06 33 02-Oct-06 12 14-Oct-06 4 39008 10 28-Oct-06 190 09-May-07 609 88.62 98.00 126.00 18-Jan-09 344 06-Jul-09 P ICB PRIOR 01-Sep-05 21 22-Sep-05 7 29-Sep-05 30 29-Oct-05 30 28-Nov-05 21 19-Dec-05 14 03-Jan-06 28 21-Apr-06 609 23-Jan-08 R ICB PRIOR 30-Apr-06 14 14-May-06 14 28-May-06 49 02-Sep-06 35 07-Oct-06 14 21-Oct-06 28 18-Nov-06 14 02-Dec-06 35 06-Jan-07 28 03-Feb-07 609 04-Oct-08 A ICB PRIOR 30-Apr-06 61 30-Jun-06 15 15-Jul-06 15 30-Aug-06 33 02-Oct-06 33 04-Nov-06 3 39028 9 16-Nov-06 145 09-Apr-07 609 81.68 77.39 104.00 09-Dec-08 311 13-Jun-09 P ICB PRIOR 01-Aug-05 15 16-Aug-06 7 23-Aug-06 30 22-Sep-06 30 22-Oct-06 21 12-Nov-06 15 27-Nov-06 30 27-Dec-06 730 16-Dec-08 F R NCB POST 30-Jan-06 7 06-Feb-06 28 06-Mar-06 21 25-Mar-06 21 15-Apr-06 14 29-Apr-06 14 13-May-06 730 12-May-08 A NCB POST 28-Jan-06 7 04-Feb-06 28 04-Mar-06 1 05-Mar-06 1 06-Mar-06 5 11-Mar-06 248 13-Nov-06 730 67.62 84.31 103.00 13-Nov-08 328 06-Apr-09 P NCB POST 01-Jun-05 7 08-Jun-05 30 08-Jul-05 30 07-Aug-05 7 14-Aug-05 14 28-Aug-05 24 21-Sep-05 365 16-Sep-06 F R NCB POST 15-Jan-06 7 22-Jan-06 28 19-Feb-06 21 13-Mar-06 21 04-Apr-06 14 18-Apr-06 14 28-Apr-06 730 28-Apr-08 A NCB POST 16-Jan-06 7 23-Jan-06 28 20-Feb-06 189 22-Aug-06 19 14-Sep-06 27 18-Sep-06 55 12-Nov-06 730 40.15 45.22 60.00 12-Nov-08 295 30-Aug-09 P NCB POST 30-Sep-05 21 21-Oct-05 7 28-Oct-05 29 27-Nov-05 30 27-Dec-05 21 17-Jan-06 15 01-Feb-06 30 03-Mar-06 540 25-Aug-07 R A P NCB POST 01-Oct-05 01-Oct-05 7 08-Oct-05 29 07-Nov-05 30 07-Dec-05 07-Dec-05 14 22-Dec-05 30 21-Jan-06 730 5-Jan-o8 R A P NCB POST 01-Sep-07 7 08-Sep-07 30 08-Oct-07 30 07-Nov-07 15 22-Nov-07 30 22-Dec-07 545 14-Jun-09 F R NCB POST 08-Oct-05 7 15-Oct-05 35 19-Nov-05 21 10-Dec-05 21 31-Dec-05 14 14-Jan-06 14 28-Jan-06 730 28-Jan-08 A NCB POST 08-Oct-05 7 15-Oct-05 35 19-Nov-05 28 15-Dec-05 27 10-Jan-06 12 22-Jan-06 41 05-Mar-06 14 19-Mar-06 730 51.81 62.08 83.00 05-Mar-08 418 26-Apr-09 P NCB POST 01-Nov-05 15 16-Nov-05 7 23-Nov-05 30 23-Dec-05 30 22-Jan-06 21 12-Feb-06 15 27-Feb-06 30 29-Mar-06 720 18-Mar-08 R NCB POST 06-Aug-06 7 13-Aug-06 35 17-Sep-06 14 01-Oct-06 21 22-Oct-06 21 12-Nov-06 14 26-Nov-06 510 20-May-08 A NCB POST 25-Sep-06 7 02-Oct-06 33 06-Nov-06 26 02-Dec-06 11 39064 12 23-Dec-06 182 30-Jun-07 510 97.38 101.18 125.00 21-Nov-08 P ICB PRIOR 7 08-Nov-06 30 08-Dec-06 31 07-Jan-07 14 22-Jan-07 30 21-Feb-07 720 10-Feb-09 R ICB PRIOR 20-Dec-07 14 03-Jan-08 14 17-Jan-08 42 28-Feb-08 14 13-Mar-08 7 20-Mar-08 14 03-Apr-08 14 17-Apr-08 21 08-May-08 7 15-May-08 450 08-Aug-09 A ICB PRIOR 12-Jan-08 14 26-Jan-08 4 30-Jan-08 42 12-Mar-08 89 09-Jun-08 12 21-Jun-08 33 24-Jul-08 40 02-Sep-08 58 30-Oct-08 670 87.73 107.29 117.00 30-Jul-10 P NCB POST R NCB POST 15-Oct-07 7 22-Oct-07 28 19-Nov-07 14 03-Dec-07 14 17-Dec-07 21 08-Jan-08 7 15-Jan-08 730 15-Jan-01 A NCB POST A ICB PRIOR 05-Mar-08 10 15-Mar-08 50 04-May-08 123 09-Aug-08 9 18-Aug-08 7 27-Sep-08 2 29-Sep-08 328 23-Aug-09 730 44.89 33.18 34.00 23-Aug-11 P ICB PRIOR R ICB PRIOR 01-Oct-09 14 15-Oct-09 14 29-Oct-09 42 10-Dec-09 14 24-Dec-09 7 31-Dec-09 14 14-Jan-10 14 28-Jan-10 21 18-Feb-10 7 25-Feb-10 600 20-Sep-10 A ICB PRIOR 01-Mar-10 P NCB POST F R NCB POST 07-Jan-06 14-Jan-06 28 11-Feb-06 21 05-Apr-06 21 26-Apr-06 14 10-May-06 14 08-May-06 810 26-Jul-08 A NCB POST 05-Feb-06 7 12-Feb-06 31 15-Mar-06 37 20-Apr-06 0 20-Apr-06 4 24-Apr-06 14 08-May-06 810 89.23 94.90 117.00 17-Oct-08 173 02-Jun-09 P NCB POST R NCB POST 01-May-06 7 08-May-06 35 12-Jun-06 21 03-Jul-06 21 24-Jul-06 14 07-Aug-06 14 21-Aug-06 810 08-Nov-08 A NCB POST 07-Jun-06 7 14-Jun-06 35 19-Jul-06 32 20-Aug-06 16 05-Sep-06 6 11-Sep-06 19 30-Sep-06 810 81.34 85.72 99.00 17-Dec-08 255 28-Aug-09 Total cost water (2) the third possess of tendering is started P NCB POST 30-Nov-05 7 07-Dec-05 28 06-Jan-06 30 05-Feb-06 05-Feb-06 15 20-Feb-06 30 22-Mar-06 720 11-Mar-08 R NCB POST 30-Nov-06 7 07-Dec-06 28 04-Jan-07 14 18-Jan-07 7 25-Jan-07 14 08-Feb-07 21 28-Feb-07 7 07-Mar-07 730 06-Mar-09 A NCB POST 09-Dec-06 7 16-Dec-06 29 14-Jan-07 54 15-Mar-07 60 14-May-07 78 30-Jul-07 21-Apr-08 730 51.8 66.86 94.00 21-Apr-10 212 11-Nov-09 P NCB POST 01-Jul-05 7 08-Jul-05 29 07-Aug-05 30 06-Sep-05 14 21-Sep-05 30 21-Oct-05 720 11-Oct-07 R NCB POST 01-Dec-06 7 08-Dec-06 28 05-Jan-07 14 19-Jan-07 14 02-Feb-07 21 23-Feb-07 14 09-Mar-07 780 27-Apr-09 RW3 2.1-Rehabilitation ZA2/06 (1)Permisible delayes Water Works RW1 RW2 2-Rehabilitation -ZA1/06 RW4 2.2-Rehabilitation -P22- ZA3/06 RW5 2.3-Rehabilitation-P23-ZA4/05 RW11 7-Lakan Reservoir 30000 m3 RW7 4-Extension-Integrated in RW1 to RW5 RW8 5-Extension Mains-P5/05 RW6 3-Extension-Integrated inRW1 to RW5 RW9 6-Extension of Lakan Submains RW10 6.1-Extension of Lakan Mains(800-1000mm) RW12 8-Distribution System Control & Instrumentation RW13 40000 m3 Reservoir of Water Tower No.2 -RT3/06 F *Sum of Actal Cost /Estimated Cost F- First Years Implemantation Packages Wastewater Works (1)The principle of permiseble delyes is contract award date The plan dated in preliminary procurement plan , has been written , one year before the loan effectiveness (Oct 25 05)and we did not staretd the works. RW14 40000 m3 Reservoir of Water Tower No.3-RT3/06 RSS1 4-Extension E1 RSS2 4.1-Extension E2 Page 6 A NCB POST 09-Dec-06 7 16-Dec-06 30 15-Jan-07 120 16-May-07 200 39418 4 06-Dec-07 20-Apr-08 780 84.64 94.86 117.00 20-jun-010 P NCB POST 01-Jan-06 7 08-Jan-06 31 07-Feb-06 30 09-Mar-06 15 24-Mar-06 31 23-Apr-06 720 12-Apr-08 R NCB POST 01-Dec-06 7 08-Dec-06 35 12-Jan-07 14 26-Jan-07 14 23-Feb-07 21 16-Mar-07 7 23-Mar-07 750 11-Apr-09 A NCB POST 09-Dec-06 7 16-Dec-06 31 16-Jan-07 52 15-Mar-07 116 09-Jul-07 20 29-Jul-07 21-Apr-08 750 41.44 82.73 70.00 21-Jun-10 209 13-Nov-09 P NCB PRIOR 01-Jul-05 7 08-Jul-05 30 07-Aug-05 30 06-Sep-05 15 21-Sep-05 30 21-Oct-05 720 11-Oct-07 F R NCB PRIOR 20-Jul-05 40 29-Aug-05 23 21-Sep-05 31 22-Oct-05 21 12-Nov--5 14 26-Nov-05 21 31-Jan-06 10 10-Feb-06 14 24-Feb-06 14 19-Mar-06 1156 18-May-09 A NCB PRIOR 20-Jul-05 40 29-Aug-05 23 21-Sep-05 30 22-Oct-05 21 13-Dec-05 28 10-Jan-06 12 22-Jan-06 42 05-Mar-06 148 01-Aug-06 1156 47.94 86.90 102.00 01-Oct-09 378 07-May-10 P NCB POST 01-Jul-05 7 08-Jul-05 31 07-Aug-05 30 06-Sep-05 15 21-Sep-05 30 21-Oct-05 720 11-Oct-07 F R NCB POST 30-Oct-05 7 06-Nov-05 35 11-Dec-05 21 01-Jan-06 21 25-Jan-06 14 08-Feb-06 14 22-Feb-06 1156 23-Apr-09 A NCB POST 23-Oct-05 14 06-Nov-05 35 11-Dec-05 45 25-Jan-06 31 25-Feb-06 4 01-Mar-06 228 16-Oct-06 1156 72.11 103.86 135.00 16-Dec-10 169 27-May-09 P NCB PRIOR 01-Aug-05 01-Aug-05 7 08-Aug-05 31 07-Sep-05 30 07-Oct-05 07-Oct-05 14 22-Oct-05 30 21-Nov-05 720 11-Nov-07 F R NCB PRIOR 25-Jul-05 35 29-Aug-05 23 21-Sep-05 31 22-Oct-05 21 12-Nov-05 14 26-Nov-05 21 17-Dec-05 14 31-Dec-05 14 14-Jan-06 14 19-Mar-06 609 18-Nov-07 A NCB PRIOR 20-Jul-05 39 29-Aug 23 21-Sep-05 31 22-Oct-05 78 08-Jan-06 30 07-Feb-06 15 22-Feb-06 11 05-Mar-06 33 08-May-06 600 100.00 103.43 123.00 05-Dec-07 72 13-Jan-08 Re-tender Pre-Qualification step A ICB PRIOR 01-Oct-07 14 09-Oct-07 6 15-Oct-07 68 22-Dec-07 42 10-Feb-08 23-Sep-08 P NCB POST 01-Sep-05 7 08-Sep-05 30 08-Oct-05 31 07-Nov-05 0 07-Nov-05 15 22-Nov-05 30 22-Dec-05 720 12-Dec-07 F R ICB PRIOR 07-Apr-08 14 21-Apr-08 14 05-May-08 42 16-Jun-08 14 30-Jun-08 7 07-Jul-08 14 21-Jul-08 14 04-Aug-08 21 25-Aug-08 7 01-Sep-08 730 01-Sep-10 A ICB PRIOR 15-Aug-08 14 28-Aug-08 51 18-Oct-08 94 20-Jan-09 76 06-Apr-09 A ICB PRIOR 25-Jun-09 24 19-Jul-09 26 14-Aug-09 06-Oct-09 109 23-Jan-10 4 27-Jan-10 12 09-Feb-10 22 02-Mar-10 4 06-Mar-10 46 21-Apr-10 0.48 2.08 17.00 P ICB PRIOR 01-Jan-06 21 22-Jan-06 7 29-Jan-06 29 28-Feb-06 30 30-Mar-06 30 29-Apr-06 6 05-May-06 30 04-Jun-06 720 24-May-08 F R ICB PRIOR 20-Mar-06 14 03-Apr-06 14 17-Apr-06 49 05-Jun-06 35 10-Jul-06 14 24-Jul-06 28 21-Aug-06 14 04-Sep-06 35 23-Oct-06 28 20-Nov-06 780 09-Jan-09 A ICB PRIOR 20-Mar-06 75 03-Jun-06 20 23-Jul-06 28 19-Aug-06 13 01-Sep-06 4 05-Sep-06 0 6 11-Sep-06 63 13-Nov-06 780 18.8 19.40 38.00 02-Jan-09 Re-tender P NCB POST 01-Oct-05 7 08-Oct-05 31 07-Nov-05 30 07-Dec-05 14 22-Dec-05 30 21-Jan-06 749 12-Jul-08 R ICB PRIOR 15-Dec-09 7 22-Dec-09 28 13-Jan-10 14 27-Jan-10 14 10-Feb-10 21 02-Mar-10 7 09-Mar-10 730 09-Mar-12 A ICB PRIOR 01-Oct-09 40 10-Nov-09 42 22-Dec-09 03-Jan-10 33 25-Jan-10 13 09-Feb-10 14-Mar-10 480 71.42 71.37 38.00 14-Jun-11 11-Extension "V"- P11-ZV/06 P NCB POST 01-Jul-05 7 08-Jul-05 31 07-Aug-05 31 06-Sep-05 06-Sep-05 15 21-Sep-05 30 21-Oct-05 542 14-Apr-07 R NCB POST 31-May-06 7 07-Jun-06 35 25-Aug-06 21 15-Sep-06 21 06-Oct-06 14 20-Oct-06 14 03-Nov-06 609 04-Jul-08 NCB POST 15-May-06 7 22-May-06 35 26-Jun-06 22 18-Jul-06 16 05-Aug-06 12 17-Aug-06 62 16-Oct-06 609 100.00 99.67 105.00 15-Jun-08 249 05-Jan-09 P 7.1- Extension "Microtunlling R ICB PRIOR 01-Jan-10 A ICB PRIOR 01-Jan-10 25-Jan-10 02-Feb-10 16-Mar-10 95 15-Jun-10 2 17-Jun-10 jun-27-10 19 15-Jun-10 Extention "X1"-P9-ZX1/06(the remained area of package RSS8) R ICB PRIOR 01-Jan-10 14 15-Jan-10 14 28-Jan-10 28 25-Feb-10 14 11-Mar-10 14 26-Mar-10 28 22-Apr-10 14 06-May-10 35 11-Jun-10 28 09-Jul-10 ICB PRIOR 15-Apr-10 17 02-May-10 9 11-May-10 74 22-Jul-10 11-Aug-10 13 24-Aug-10 4 28-Aug-10 P NCB POST 01-Jul-05 7 08-Jul-05 31 07-Aug-05 30 06-Sep-05 06-Sep-05 15 21-Sep-05 30 21-Oct-05 542 14-Apr-07 F R ICB PRIOR 01-Jan-10 7 07-Jan-10 28 04-Feb-10 14 18-Feb-10 14 04-Mar-10 14 18-Mar-10 7 25-Mar-10 485 23-Jul-11 A ICB PRIOR 10-May-10 9 19-May-10 6 25-May-10 53 17-Jul-10 24 10-Aug-10 5 15-Aug-10 16 31-Aug-10 P NCB POST 01-Jul-05 7 08-Jul-05 30 07-Aug-05 30 06-Sep-05 15 21-Sep-05 30 21-Oct-05 542 14-Apr-07 F R NCB POST 20-Jun-08 7 27-Jun-08 28 25-Jul-08 14 08-Aug-08 14 22-Aug-08 21 12-Sep-08 7 19-Sep-08 542 15-Mar-10 A ICB PRIOR 25-Oct-08 14 08-Oct-08 28 04-Nov-08 262 24-Jul-09 3 27-Jul-09 6 03-Aug-09 30 03-Sep-09 29-Sep-09 600 45.26 23.23 37.00 29-Jun-11 P ICB PRIOR 01-Sep-05 21 22-Sep-05 7 29-Sep-05 30 29-Oct-05 30 28-Nov-05 21 19-Dec-05 14 03-Jan-06 30 02-Feb-06 540 27-Jul-07 R ICB PRIOR 01-Dec-09 14 15-Dec-09 14 29-Dec-09 42 10-Jan-10 14 24-Jan-10 7 31-Jan-10 14 14-Feb-10 14 28-Feb-10 21 21-Mar-10 7 31-Mar-10 485 29-Jul-11 A ICB PRIOR 01-Nov-09 22 23-Nov-09 8 01-Dec-09 12-Jan-10 60 14-Mar-10 15-Mar-10 3 18-Mar-10 26 26 14-Apr-10 14 28-Apr-10 485 54.72 53.85 46.00 28-Aug-11 P NCB POST 01-Oct-05 7 08-Oct-05 30 07-Nov-05 30 07-Dec-05 15 22-Dec-05 30 21-Jan-06 750 15-Jul-08 R ICB PRIOR 30-Nov-09 7 08-Dec-09 28 06-Jan-01 14 20-Jan-01 14 03-Feb-01 21 24-Feb-01 7 03-Mar-01 600 24-Oct-02 A ICB POST 15-Dec-09 13 28-Dec-09 12 10-Jan-10 58 09-Mar-10 34 12-Apr-10 22 04-May-10 8 12-May-10 39 20-Jun-10 4 24-Jun-10 600 15.00 24-Feb-12 SS9 P ICB PRIOR 01-Aug-05 21 22-Aug-05 7 29-Aug-05 30 28-Sep-05 30 28-Oct-05 21 18-Nov-05 15 03-Dec-05 29 02-Jan-06 540 26-Jun-07 R ICB PRIOR 30-Jan-08 14 13-Feb-08 14 27-Feb-08 42 09-Apr-08 14 23-Apr-08 7 30-Apr-08 14 14-May-08 14 28-May-08 21 18-Jun-08 28 16-Jul-08 730 16-Jul-10 A P NCB POST R NCB POST 28-Aug-08 7 03-Sep-08 28 01-Oct-08 14 15-Oct-08 14 29-Oct-08 21 19-Nov-08 7 26-Nov-08 900 26-May-10 A NCB POST Total cost Rasht RSS6 7-Extension "K"- P7-ZK/05 RSS3 4.2-Extension E3 RSS4 5-Extension "I" -P5-Z/05 RSS5 6-Extension"J"- P6-ZJ-05 18- Pumping Station "centra, LSD1,LSX1,PSN"-P18-PS- CA/06 SS6 19-Pumping Station "Eastern I,PSK"-P19-PS-EA/06 RSS7(2) 7.1- Extension "Microtunlling I,J&K"-P71-MT/06 RSS8 9- Extension "XI"-P9-ZXI/06 RSS9 10-Extension "Y1" RSS10 RSS11 RSS12 SS5 Total Wastewater SS7 20- Wastewater main trasmission line SS8 20.1-Pumping Station "Western PSE,PSW" 22-Emergency Reservoir "T- PLANT" SS10 Upgrading to BNR *Sum of Actal Cost /Estimated Cost Page 7 (2) the third possess of tendering is started The plan dated in preliminary procurement plan , has been written , one year before the loan effectiveness (Oct 25 05)and we did not staretd the works. (1)The principle of permiseble delyes is contract award date F- First Years Implemantation Packages Page 8 Comments (Contractor's Name & Country) AG Guilban Co / Iran Chakad-d-jonob Co/ Iran Takbam Shomal Co / Iran Jong-e-sanat Co/ Iran Porsapay Co/ Iran AbadsazanToos Co/Iran Argavanpay-kapachin Co/ Iran Porsapay Co/ Iran Aryaniro Co/Iran Avindegh Co/Iran Pars Way Co/Iran the first pp does not include the plan cost and dates Naderan Sazan+ EvanBastan Co/Iran the first pp does not include the plan cost and dates the first pp doesnot incliude the plan cost and dates Goharrod Co/ Iran the first pp does not incliude the plan cost and dates Pakoh Co/Iran Vahdat Lorestan Co / Iran This contract has been combined in the RW1,2,3,4,5 contracts This contract has been combined in the RW1,2,3,4,5 contracts Page 9 Moshe Sanat Co/Iran Vahdat Lorestan Co/Iran Sadrahe Gaskar Co/Iran Kapachin Co/Iran Chakadjonob Co/Iran based on the Wb e-mail datedSep 23,2008it was aggred to re-tender Moshref + kayson- Sakokar +Lowshan + Mishion - Ostash + mts= parsway co+ Dayen Co based on the Wb e-mail dated Jun20,2009 of WB it was aggred to re-tender Jyane Construction & AGD-Iseki Shvak Co- Due to poor performance this contrctor has been terminated Sep 24-08 by clioent based on the E-mail dated Sep 11,2008 the WB & due to reduced scope of work to reject all the bids and re-tender this reduced scope of work Balarnasb Co/Iran Balarnasb Co/Iran Jyane Construction & AGD-Iseki JV Porsapay & Moshsanat/Iran Gostaresh Sanat Iran/Iran Moeen Pajhohesh / Iran Takbam Shomal / Iran Parsway + Teknozist Co/Iran This contract will be done in next phase This contract will be done in next phase Page 10 Page 11 Iran- P076884- Northern Cities Water & Sanitation Anzali Procurement Plan as of October 31, 2010 Sl. # Tender Number Package Name/ Contract ID. No. Plan /Revised/Actual Procurement Method Review By Bank (PRIOR /Post) Submission/ Readiness Date Interval /d WB No Objection Date Interval /d Invitation Date Interval /d Expected Bid-Opening Date Interval /d Evaluation & Recomm. Interval /d W B No Objection Date Interval /d Contract Finalisation Interval /d WB No Objection Date Interval /d Contract Signature Date Interval /d Start Date Execution /b Progress (%) Disburesment with adjusment & Advance Payment Disburesment with out adjusment & Completion Date Comments (Contractor's Name & cuntry ) Interval /d C omple t ion D ate A B C E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD AE AF AG P NCB POST 30,sep,06 21 21-Oct-06 7 28-Oct-06 30 27-Nov-06 30 27-Dec-06 21 17-Jan-07 14 01-Feb-07 31 03-Mar-07 543 24-Aug-08 R NCB POST 15-Apr-06 7 22-Apr-06 35 27-May-06 21 28-Jun-06 21 19-Jul-06 14 02-Aug-06 14 16-Aug-06 660 06-Jun-08 1-267 16-Mar-09 2-100 24-Jun-09 P NCB POST 01-Sep-06 7 08-Sep-06 30 08-Oct-06 30 07-Nov-06 15 22-Nov-06 30 22-Dec-06 539 14-Jun-08 R NCB POST 15-Jul-06 7 22-Jul-06 35 26-Aug-06 21 16-Sep-06 21 07-Oct-06 14 21-Oct-06 14 04-Nov-06 609 05-Jul-08 A NCB POST 15-Jul-06 7 23-Jul-06 31 30-Aug-06 22 21-Sep-06 4 25-Sep-06 7 02-Oct-06 14 16-Oct-06 609 102.60 120.00 104.03 20-Jun-08 317 29-May-09 Absar Co/Iran P NCB POST 01-Mar-06 01-Mar-06 7 08-Mar-06 31 07-Apr-06 30 07-May-06 15 22-May-06 30 21-Jun-06 719 . 10-Jun-08 R NCB POST 15-Apr-07 7 22-Apr-07 28 20-May-07 14 03-Jun-07 14 17-Jun-07 21 08-Jul-07 7 15-Jul-07 609 15-Mar-09 A NCB POST 15-Oct-06 7 22-Oct-06 28 26-Nov-06 19 Dec-16-06 161 26-May-07 68 02-Aug-07 141 26-Dec-07 609 115.40 157.00 110.65 26-Jun-09 125 20-Sep-09 Gil Farazsazeh Co/Iran P NCB POST 01-Sep-06 15 16-Sep-06 7 23-Sep-06 30 23-Oct-06 30 22-Nov-06 21 13-Dec-06 15 28-Dec-06 30 27-Jan-07 539 20-Jul-08 R NCB POST 15-Jul-07 7 22-Jul-07 28 19-Aug-07 14 02-Sep-07 14 16-Sep-07 21 07-Oct-07 7 14-Oct-07 609 14-Jun-09 A NCB POST 15-Oct-06 7 22-Oct-06 29 27-Nov-06 30 27-Dec-06 28 23-Jan-07 194 05-Aug-07 132 13-Dec-07 609 104.00 136.00 113.90 13-Jun-09 291 04-Apr-10 Mehersaze Tonkabon P NCB POST 01-Jun-05 7 08-Jun-05 30 08-Jul-05 29 07-Aug-05 15 22-Aug-05 30 21-Sep-05 360 16-Sep-06 F R NCB POST 15-Jan-06 7 22-Jan-06 28 19-Feb-06 21 12-Mar-06 21 02-Apr-06 14 16-Apr-06 14 30-Apr-06 553 04-Nov-07 A NCB POST 15-Jan-06 7 22-Jan-06 28 19-Feb-06 180 18-Aug-06 33 20-Sep-06 0 20-Sep-06 13 03-Oct-06 553 80.61 97.00 71.79 01-Apr-08 1-182 08-Oct-08 Pakoh C0/Iran 35 13-Nov-08 P NCB POST 01-Jan-07 7 08-Jan-07 29 07-Feb-07 30 09-Mar-07 14 24-Mar-07 30 23-Apr-07 360 17-Apr-08 R NCB POST 01-Sep-09 7 08-Sep-09 28 26-Oct-09 14 09-Nov-09 14 23-Nov-09 21 14-Dec-09 7 21-Dec-09 553 21-Apr-01 A NCB POST (1) The prequalification of this package will be conducted prior to completion of the Bidding Document. * Sum of Actal Cost /estimated Cost F- First Year Implementation packages Exchange rate: US$ 1= IRR 9200 P NCB POST 30-Sep-06 21 21-Oct-06 7 28-Oct-06 31 27-Nov-06 30 27-Dec-06 21 17-Jan-07 15 01-Feb-07 30 03-Mar-07 719 20-Feb-09 R NCB POST 16-Jan-07 7 23-Jan-07 28 20-Feb-07 14 06-Mar-07 14 20-Mar-07 21 10-Apr-07 7 17-Apr-07 854 21-Jul-09 A NCB POST 23-Dec-06 7 30-Dec-06 29 28-Jan-07 11 08-Feb-07 144 03-Jun-07 64 05-Aug-07 138 19-Dec-07 730 58.66 102 81.90 19-Dec-09 Abadsazan tos Co / Iran P ICB PRIOR 30-Sep-06 7 07-Oct-06 30 06-Nov-06 30 06-Dec-06 15 21-Dec-06 30 20-Jan-07 720 09-Jan-09 F R ICB PRIOR 01-Sep-07 14 15-Sep-07 14 29-Sep-07 42 10-Nov-07 14 24-Nov-07 7 01-Dec-07 14 15-Dec-07 14 29-Dec-07 21 19-Jan-08 7 26-Jan-08 854 26-Apr-10 A ICB PRIOR 26-Aug-07 10-Nov-07 22 02-Dec-07 20 22-Dec-07 29-Jan-08 38 4 02-Feb-08 0 02-Feb-08 780 69 93 82.62 2-May-010 Absar Co /Iran P NCB POST 30-Jul-07 7 06-Aug-07 31 05-Sep-07 30 05-Oct-07 15 20-Oct-07 30 19-Nov-07 539 12-May-09 F R NCB POST 28-Feb-06 7 07-Mar-06 28 04-Apr-06 21 25-Apr-06 21 16-May-06 14 30-May-06 14 13-Jun-06 575 09-Jan-08 A NCB POST 28-Jan-06 7 04-Feb-06 28 04-Mar-06 85 28-May-06 28 25-Jun-06 50 14-Aug-06 18 01-Sep-06 575 110.51 129.00 106.46 01-Apr-08 254 07-Dec-08 Gilfaraz Sazeh Co/Iran P NCB POST 01-Sep-06 16-Sep-06 23-Sep-06 07-Nov-06 07-Dec-06 28-Dec-06 12-Jan-07 11-Feb-07 539 04-Aug-08 F R NCB POST 31-May-06 7 07-Jun-06 35 12-Jul-06 21 02-Aug-06 21 23-Aug-06 14 06-Sep-06 14 20-Sep-06 810 09-Dec-08 A NCB POST 23-May-06 7 30-May-06 35 04-Jul-06 12 16-Jul-06 18 03-Aug-06 10 13-Aug-06 65 17-Oct-06 810 88.11 108.00 82.94 05-Dec-08 104 01-Mar-09 Pakoh C0/Iran P NCB POST 01-Jan-06 7 08-Jan-06 29 07-Feb-06 30 09-Mar-06 15 24-Mar-06 30 23-Apr-06 719 12-Apr-08 F R NCB POST 20-Aug-07 7 27-Aug-07 28 24-Sep-07 14 08-Oct-07 14 22-Oct-07 21 12-Nov-07 7 19-Nov-07 854 22-Mar-10 A NCB POST 07-Oct-07 7 14-Oct-07 42 25-Nov-07 14 09-Dec-07 16 25-Dec-07 5 30-Dec-07 20-Apr-08 547 48.08 58 48.83 30-Dec-09 95 01-Nov-09 LolehSazi Lowshan Co P NCB POST 01-Sep-05 7 08-Sep-05 30 08-Oct-05 30 07-Nov-05 15 22-Nov-05 30 22-Dec-05 547 15-Jun-07 F R NCB POST 15-Jan-06 7 22-Jan-06 28 19-Feb-06 21 12-Mar-06 21 02-Apr-06 14 16-Apr-06 14 30-Apr-06 810 18-Jul-08 A NCB POST 15-Jan-06 7 22-Jan-06 28 19-Feb-06 182 22-Aug-06 22 13-Sep-06 5 18-Sep-06 167 02-Mar-07 810 62.2 80.00 52.75 02-Jun-09 155 23-May-09 Pakoh C0/Iran P NCB POST 01-Jul-05 15 16-Jul-05 7 23-Jul-05 14 06-Sep-05 30 06-Oct-05 21 27-Oct-05 14 11-Nov-05 30 11-Dec-05 720 01-Dec-07 R NCB POST 20-Nov-09 7 27-Nov-09 28 25-Dec-09 14 08-Jan-10 14 22-Jan-10 21 12-Feb-10 7 19-Feb-10 600 20-Oct-11 A NCB POST 01-Jan-10 19-Jan-10 02-Mar-10 29-Mar-10 57 25-May-10 20 13-Jun-10 9 22-Jun-10 668 Sanatzaman Co/Iran P NCB POST 01-Jun-05 15 16-Jun-05 7 23-Jun-05 45 07-Aug-05 30 06-Sep-05 21 27-Sep-05 15 12-Oct-05 30 11-Nov-05 720 01-Nov-07 F R ICB PRIOR 20-Nov-09 7 27-Nov-09 28 25-Dec-09 14 08-Jan-10 14 22-Jan-10 21 12-Feb-10 7 19-Feb-10 600 12-Oct-11 A ICB PRIOR 15-Jun-10 10 25-Jun-10 03-Jul-10 58 31-Aug-10 P NCB POST 01-Jun-07 7 08-Jun-07 30 08-Jul-07 30 07-Aug-07 15 22-Aug-07 30 21-Sep-07 720 10-Sep-09 Permiseble delyes Water Works AW1 1-Extension & Rehabilitation AN-1 A NCB POST 15-Apr-06 22 03-Aug-06 18 03-May-06 35 07-Jun-06 35 12-Jul-06 21-Jun-08 TakbamShomal Co/ Iran 16 19-Aug-06 48 06-Nov-06 609 114.73 131.00 113.01 Total Cost Water Works the plan dated of preliminary procurment plan has been written one year before the loan effectiveness dated (Oct25 05) and we did not started the works . AW2 2-Extension & Rehabilitation AN-2 AW3 3-Extension & Rehabilitation GH-1 AW4 4-Extension & Rehabilitation GH-2 AW5 5&6-Extension- P56/05 AG6 7-Instrumentation ( Goods ) AWW6 8-Extension Eastern "A"&"D"-P8- ZAD/05 Wastewater Works AWW1 3-Extension Eastern "B"&"E"-P3-ZBE/06 AWW2 4-Extension Eastern "C"-P4-ZC/06 AWW3 5-Extension Eastern "G"-P5-ZG/06 AWW4 6-Extension Eastern "F"-P6-ZF/06 AWW5 7-Extension Western "9"-Z9/06 AWW7 12-Pumping Stations in Eastern Area AWW8 13-Pumping Stations in Western Area 16-Biological BNR This contract Page 12 R NCB POST 20-Nov-09 7 27-Nov-09 28 25-Dec-09 14 08-Jan-10 14 22-Jan-10 21 12-Feb-10 7 19-Feb-10 730 19-Feb-12 A NCB POST P NCB POST 01-Jun-07 7 08-Jun-07 30 08-Jul-07 30 07-Aug-07 15 22-Aug-07 30 21-Sep-07 539 14-Mar-09 R NCB POST 30-Jan-08 7 06-Feb-08 28 06-Mar-08 14 20-Mar-08 14 03-Apr-08 21 24-Apr-08 7 01-May-08 630 21-Jan-10 A NCB POST AWW11 Pre-Qualification step A ICB PRIOR 01-Sep-06 20 21-Sep-06 52 11-Nov-06 50 30-Dec-06 259 15-Sep-07 5 20-Sep-07 1-Oztas co 2- JV moshref + kayson- vijheh+Absar co 3- Balagar Co 4- JV Chlub+Technoz ist Co 5- JV Behradpardis co + Hightecninter P ICB POST 30-Jun-05 7 07-Jul-05 30 06-Aug-05 30 05-Sep-05 15 20-Sep-05 30 20-Oct-05 360 15-0ct-06 F R ICB PRIOR 20-Jul-07 14 03-Aug-07 14 17-Aug-07 42 27-Sep-07 14 11-Oct-07 7 18-Oct-07 14 01-Nov-07 14 15-Nov-07 21 06-Dec-07 7 13-Dec-07 915 15-Jun-10 A ICB POST 01-Sep-08 10.00 10-Sep-08 28.00 07-Oct-08 96.00 11-Jan-09 12-May-09 6 18-May-09 3 21-May-09 28-Jul-09 12-Aug-09 18 01-Sep-09 1260 29.38 21.00 15.10 01-Sep-13 JV Mushrif + kayson/ P NCB POST 30-Jan-06 7 06-Feb-06 30 08-Mar-06 30 07-Apr-06 15 22-Apr-06 30 22-May-06 360 17-May-07 R NCB POST 01-Sep-09 7 07-Sep-09 28 05-Oct-09 14 19-Oct-09 14 02-Nov-09 21 23-Nov-09 7 30-Nov-09 280 06-Sep-10 A NCB POST (1) The prequalification of this package will be conducted prior to completion of the Bidding Document. * Sum of Actal Cost /estimated Cost F- First Year Implementation packages Exchange rate: US$ 1= IRR 9200 AWW11 18-WWTP GHAZIAN (1) -P18- WWTP/06 AWW9 16-Biological BNR Plant will be done in next phase AWW10 17-Emergency Reservoir This contract will procured by local budget This contract will be done by govern share Total Cost Wastewater Works Total Cost Anzali The principle of the plan dated of preliminary procurment plan has been written one year before the loan effectiveness dated (Oct25 05) and we did not started the works . AWW12 19-Power Lines to WWTP(S&I)
Groupe de la Banque mondiale · Procurement Plan
Iran - Northern Cities Water Supply and Sanitation Project : procurement plan
Voir le document original
Le texte intégral est hébergé par l’organisation qui le publie. lawenc.com indexe les métadonnées et renvoie vers la source officielle.
Texte intégral
Informations clés
Organisation
Groupe de la Banque mondiale
Type de document
Procurement Plan
Source
Banque mondiale