Page 1 Procurement Plan for Consultant Services YEMEN P065111: Ports Cities Development Program IDA.37290 ** Applicable in case of Bank's prior review SL No. Package/ Reference No. Description of Services Review by Bank (Prior/ Post) Type of Consultant (Firm/ Individual) Method of Selection Advertising for Short listing (Date) TOR/Shortli st to be Finalised (Date) RFP Final Draft to be forwarded to the Bank (Date) No Objection from Bank for TOR (Date)** No Objection from Bank for Shortlist (Date)** No Objection from Bank for Final RFP (Date)** RFP Issued (Date) Proposal Submission Deadline (Date) No Objection by the Bank to the Technical Evaluation Report (Date)** No Objection by the Bank (Technical/ #Combined/ Draft Contract/ Final Contract) (Date)** Contract Signed (Date) Contract Value Contract Currency Contract No. Name, City, and Country of Contractor (incl. Zip Code if US) Services Completion (Date) Expenses Incurred to Date Comments Planned 25Nov2002 15Dec2002 15Dec2002 25Dec2002 N/A 25Dec2002 1Jan2003 10Feb2003 N/A 15Mar2003 5April2003 15Oct2003 Revised Prior Firm QCBS 25Nov2002 15Dec2002 15Dec2002 25Dec2002 N/A 25Dec2002 1Jan2003 10Feb2003 N/A 15Mar2003 5April2003 30Nov2006 Actual 18Feb2003 23May2003 14June2003 14June2003 N/A 14June2003 1July2003 26July2003 N/A 16Oct2003 6Lune2004 31Mar2007 Planned 15June2003 15July2003 40009 25July2003 N/A 25July2003 30July2003 15Sep2003 N/A 20Oct2003 25Oct2003 25Oct2004 Revised Prior Firm QCBS 15June2003 15July2003 40009 25July2003 N/A 25July2003 30July2003 15Sep2003 N/A 20Oct2003 25Oct2003 7june2004 Actual 7July2003 8Sep2003 20Sep2003 28Sep2003 N/A 28Sep2003 5Oct2003 10Dec2003 N/A 28Feb2004 7June2004 17Dec2005 Planned N/A 7April2004 20April2004 24April2004 N/A 24April2004 30April2004 N/A N/A 19April2004 38110 21June2004 Revised Prior Individual CQ N/A 7April2004 20April2004 24April2004 N/A 24April2004 30April2004 N/A N/A 20April2004 3May2004 21June2004 Actual N/A 20Mar2004 20Mar2004 22Mar2004 N/A 22Mar2004 N/A N/A N/A 14May2004 17April2004 31May2004 Planned 5Aug2004 15Sep2004 N/A 25Sep2004 N/A N/A N/A N/A N/A 15Oct2004 20Oct2004 N/A Revised Prior Individual QCBS 5Feb2005 15Mar2005 7Mar2005 15Mar2005 N/A 15Mar2005 20Mar2005 5May2005 N/A 27May2005 1Aug2005 1,200,000.00 $ 20June2007 Actual 5Feb2005 14Oct2005 11Oct2005 20Nov2005 N/A 20Nov2005 21Nov2005 20Dec2005 N/A Planned N/A 7April2004 20April2004 24April2004 N/A 24April2004 30April2004 N/A N/A 30April2004 3May2004 N/A Revised Prior Individual CQ N/A 7April2004 20April2004 24April2004 N/A 24April2004 30April2004 14April2004 N/A 30April2004 3May2004 Feroza N/A Actual N/A 20Mar2004 20Mar2004 22Mar2004 N/A 22Mar2004 N/A 8May2004 N/A 19May2004 17April2004 $ 31May2004 5,220.00 Planned N/A 30March2004 N/A N/A N/A N/A N/A N/A N/A 15April2004 15May2004 Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 10Jan2005 Revised Prior Individual SS N/A N/A 8May2004 10May2004 N/A 10May2004 N/A N/A 15Aug2004 30Aug2004 10Sep2004 $ Bijan 10Jan2005 Actual N/A N/A 27Aug2003 27Aug2003 N/A 27Aug2003 N/A N/A 21July2004 15Sep2004 30Dec2005 Planned 28April2004 20June2004 10July2004 20July2004 N/A 20July2004 25July2004 5Sep2004 10Oct2004 10Oct2004 20Oct2004 20Oct2005 Revised Prior Firm QCBS 28April2004 20June2004 10July2004 20July2004 N/A 20July2004 25July2004 5Sep2004 10Oct2004 15Oct2004 20Oct2004 $ Ramboll 15Nov2005 Actual 28Aug2004 20Sep2004 16Sep2004 20Sep2004 N/A 20Sep2004 22Sep2004 1Dec2004 1Mar2005 25Feb2005 14Mar2005 14Oct2005 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 30Oct2005 Revised Prior Individual SS N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ 30Oct2005 Actual N/A N/A N/A N/A N/A N/A N/A N/A 11Sep2003 N/A 10Sep2003 Dr.Sameh 25April2004 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual QCBS N/A 1Mar2005 1Mar2005 1Mar2005 N/A 1Mar2005 N/A N/A 12Mar2005 15Mar2005 16Mar2005 $ David Sims 31Dec2006 Actual N/A N/A 14Feb2005 14Feb2005 N/A 14Feb2005 N/A N/A N/A N/A 6April2005 31Mar2007 Planned 15Sep2004 N/A N/A N/A N/A 25Sep2004 N/A N/A N/A 15Oct2004 20Oct2004 20Feb2005 Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ 31Mar2006 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 1April2005 30June2007 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A 10Oct2004 N/A N/A 3Nov2004 $ 28Feb2005 Actual N/A N/A N/A N/A N/A N/A N/A 24Oct2004 N/A N/A 6Nov2004 28Feb2005 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 20Nov2004 Revised Post Firm CQ N/A 25July2004 N/A N/A N/A N/A N/A 1June2004 N/A N/A 20Aug2004 $ 1Nov2004 Actual N/A N/A N/A N/A N/A N/A N/A 12June2004 N/A N/A 1Sep2004 Terminated Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 25Jan2005 $ 25Mar2005 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 25Jan2005 $ 25Mar2005 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 25Jan2005 $ 25Mar2005 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 30Jan2005 30Mar2005 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Prior Firm SS N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 20Mar2005 3April2005 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Firm SS N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ Actual N/A N/A N/A N/A N/A N/A N/A 15Feb2005 N/A N/A 24Aug2005 31Jan2006 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ 30April2008 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 22Mar2005 30April2008 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 10Aug2005 $ 31Dec2005 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 15April2005 31Dec2005 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ 30July2006 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 31Oct2005 30July2006 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Firm SS N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 1Jan2006 31Dec2006 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ 30June2007 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 4Feb2006 10Feb2006 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ 30Sep2006 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 1May2006 30Sep2007 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 6Oct2005 31Aug2006 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A $ Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 30July2006 20Aug2007 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Firm QCBS 10Feb2004 10Mar2004 10Mar2004 20Mar2004 20Mar2004 30Mar2004 15May2004 30June2004 10July2004 20July2004 $ 7Dec2004 Actual 7April2004 21July2004 21July2004 1Aug2004 1Aug2004 1Aug2004 9Oct2004 11Mar2005 2Aug2005 6April2005 20Jan2008 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Firm QCBS N/A N/A 15Mar2006 25Mar2006 25Mar2006 1April2006 30April2006 28May2006 20July2006 22July2006 $ 31Dec2006 Actual N/A N/A 25Mar2006 18April2006 18April2006 23April2006 31May2006 16June2006 22Aug2006 25Sep2007 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Firm QCBS $ 30June2007 Actual 18April2005 31Mar2005 16May2005 31May2005 31May2005 2June2005 18July2005 5Oct2005 25Jan2006 29Jan2006 Terminated Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual QCBS 28Nov2007 $ 30June2007 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A 1Oct2006 30June2007 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Firm SS N/A N/A Actual N/A N/A 1Aug2005 1Aug2005 N/A N/A N/A N/A N/A 1Jan2007 31Dec2007 Sami Bsaiso 27,195.00 N/A N/A Dr-Hatim Al-Kadi Kaia Miller 34,689.46 N/A Al-Asuwaidi & Lokman 2,250.00 2,250.00 N/A Tourism Development and Cultural Heritage Consultant Aditing Services(2007) 2,385.00 2,385.00 N/A Dahman RSM Dahman RSM 4,250.00 3,825.00 Mohammed Habib Sadeq 49,500.00 34,467.92 N/A 1,100.00 NVIT 330.00 Al-Asuwaidi & Lokman 175.00 157.00 N/A N/A Al-Asuwaidi & Lokman 225.00 225.00 N/A Urban Planning Consultant 194,950.00 Khalid Touqan 35,000.00 Urban Planning Consultant 194,950.00 Wahy Taha Aman 4,872.00 51,688.00 58,360.00 49,925.00 49,923.00 38,850.00 5,250.00 4,500.00 56,235.00 N/A Mohammed Al-Sayed 30 Marketing and Branding Consultant (3Cities) Workshop Documents Translation specialist Yemen Future Vision and Strategy and Role within the Region AFZ Technical Advisor 35,000.00 4,567.00 49,850.00 54,452.00 Dahman RSM 4,050.00 N/A N/A Raid Al-Khori 8,680.00 Construction Suppervision Mansoora Rotary&Sheik Othman Green Belt PCDP website 7 8 15 22 19 17 16 18 20 Translation Specialist (Bridge Survey) Resettlement plan & Social assement studies LED consultancy Services (21months) 14 13 Natural Gas utilization study Competitiveness Study (for Hod&Muka) 5 City Development Strategy Translation Specialist Advisor to support NCU for AMU 904,810.00 N/A $ 904,810.00 8,700.00 1,180,145.88 $ N/A Halcrow 687,937.00 10,000.00 $ N/A Raqiah Humeidan Aden-Yemen 1 Aden Group I Supervision for Projects Aden GroupI 2 12 N/A Zakia A. Younus 1,270.20 9 4 6 11 10 Technical (Electrical) Specialist for NCU 29 Auditing Services (2006) IT Training Center/ Assessment Revising &upgrading the Mastr plan-Hodeidah & Mukalla Study and Design for group II Projects-Aden Design Studies for the implementation of the Aden Causeway Auditing Services(2005) In some contracts, one or more of these approvals may be contained in one Bank communication. CEC-Jordan Cancelled and individual hired Auditing Services (2003-2004) Updating Master plan of Aden 1,460.00 N/A N/A Architactural Specialist for NCU N/A N/A N/A 35,000.00 16,489.00 N/A 8,000.00 Translation Specialist (Aden MP+Resetlement) Translation Specialist (Dubi Port int.) 3 Social Assessment Study(RPF) 6,000.00 21 23 24 25 26 27 28 31 589.02 680.50 1,278,425.00 Dar-Alhandasa 1,278,424.25 N/A N/A Fahmi Mahboob Hasson Hadi Pierre Saliba 10,445.00 N/A N/A 4,750.00 $ 181,500.00 N/A Carl Bro 652,530.00 711,850.00 N/A Renardeh 181,500.00 10,445.00 Dahman RSM 4,750.00 Page 2 SL No. Package/ Reference No. Description of Services Review by Bank (Prior/ Post) Type of Consultant (Firm/ Individual) Method of Selection Advertising for Short listing (Date) TOR/Shortli st to be Finalised (Date) RFP Final Draft to be forwarded to the Bank (Date) No Objection from Bank for TOR (Date)** No Objection from Bank for Shortlist (Date)** No Objection from Bank for Final RFP (Date)** RFP Issued (Date) Proposal Submission Deadline (Date) No Objection by the Bank to the Technical Evaluation Report (Date)** No Objection by the Bank (Technical/ #Combined/ Draft Contract/ Final Contract) (Date)** Contract Signed (Date) Contract Value Contract Currency Contract No. Name, City, and Country of Contractor (incl. Zip Code if US) Services Completion (Date) Expenses Incurred to Date Comments Planned N/A N/A N/A N/A N/A Revised Post Firm QCBS 15Oct2006 20Dec2006 17April2007 Actual N/A N/A N/A N/A N/A N/A N/A N/A 3Mar2007 15Feb2008 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ 30Aug2007 Actual N/A N/A 13Mar2007 12April2007 12April2007 13April2007 21April2007 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Firm QCBS N/A 3June2007 Actual 14Feb2007 4Mar2007 N/A N/A N/A N/A 5Mar2007 13Mar2007 4April2007 16Jan2008 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Firm QCBS 15June2003 28Feb2005 25Feb2005 25Feb2005 N/A 25Feb2005 1Mar2005 17April2005 27May2005 9Aug2005 14Aug2005 30Mar2006 Actual 6May2004 19June2005 19June2005 N/A 19June2005 22June2005 23Aug2005 24April2006 28Nov2006 11Dec2006 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ N/A N/A N/A N/A N/A N/A N/A N/A 30June2007 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 17Feb2007 Planned 20Dec2006 5Feb2007 5Feb2007 14Feb2007 N/A 14Feb2007 15Feb2007 31Mar2007 30April2007 20June2007 30June2007 Revised 20Dec2006 5Feb2007 5Feb2007 14Feb2007 N/A 14Feb2007 15Feb2007 31Mar2007 30April2007 20June2007 30June2007 14May2008 Actual 21Mar2007 29Aug2007 11Sep2007 13Sep2007 N/A 13Sep2007 15Sep2007 4Nov2007 11Dec2007 2Feb2008 13Mar2008 Actual Study and design for Group I Projects -Mukalla 21Mar2007 29Aug2007 11Sep2007 13Sep2007 N/A 13Sep2007 15Sep2007 4Nov2007 11Dec2007 2Feb2008 13Mar2008 572,110.00 $ N/A CES 228,844.00 Addational works 297645 Planned N/A 10July2007 10July2007 10July2007 N/A 10July2007 15AJuly2007 1Sep2007 25Sep2007 3Oct2007 15Oct2007 1,081,862.00 $ Revised N/A 10July2007 10July2007 10July2007 N/A 10July2007 15AJuly2007 1Sep2007 25Sep2007 3Oct2007 15Oct2007 1,081,862.00 $ 14Aug2008 Actual 4June2007 27July2007 27July2007 5Agu2007 N/A 5Agu2007 5Aug2007 Addational works 171,405.00 Planned 15Aug2007 16Aug2007 20Aug2007 20Aug2007 21Aug2007 7Oct2007 3Nov2007 15Dec2007 18Dec2007 Revised Prior Firm QCBS 15Aug2007 16Aug2007 20Aug2007 20Aug2007 21Aug2007 7Oct2007 3Nov2007 15Dec2007 18Dec2007 17Dec2008 Actual 11July2007 11Sep2007 13Sep2007 13Sep2007 13Sep2007 15Sep2007 31Oct2007 2Feb2008 N/A 18Sep2008 Planned 22Sep2007 22Sep2007 25Sep2007 25Sep2007 25Sep2007 6Nov2007 20Nov2007 27Nov2007 1Dec2007 Revised Prior Firm QCBS 22Sep2007 22Sep2007 25Sep2007 25Sep2007 25Sep2007 6Nov2007 20Nov2007 27Nov2007 1Dec2007 Actual 18Aug2007 4Nov2007 30Oct2007 4Nov2007 4Nov2007 5Nov2007 5Jan2008 25April2008 N/A 12May2008 05/27/2009 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Firm CQ $ Actual N/A N/A N/A N/A N/A N/A 18June2007 N/A N/A 20June2007 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Firm QCBS $ 18March2010 Actual 30June2008 8Sep2008 13Sep2008 13Sep2008 13Sep2008 5Nov2008 N/A 13May2009 18June2009 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Individual SS $ Actual 6Nov2007 N/A 2Feb2008 2Feb2008 2Feb2008 13Feb2008 16Feb2008 20Feb2008 25April2008 30April2008 62,500.00 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Individual IS Actual 30June2008 24June2008 29June2008 29|June2008 6Aug2008 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ $ 31Aug2008 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A 1Jan2008 47,000.00 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Individual CQ $ 31May2008 Actual N/A N/A N/A N/A N/A N/A N/A N/A N/A 1Nov2007 5,000.00 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Firm CQ 84,007.00 $ Al-Qadi 14Jan2009 Actual Addition works(Traffic sign) 17Sep2007 N/A N/A N/A N/A N/A 9Oct2007 N/A N/A 15Jan2008 16,800.00 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Firm CQ 17sep2007 15Oct2008 N/A N/A N/A N/A N/A 20June2009 5/july2009 5/july2009 10/July2009 15May2010 Actual 18Oct2008 13MAy2009 N/A N/A N/A N/A N/A Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Post Firm CQ N/A N/A N/A N/A N/A N/A $ Hani Alshooly 20April2008 Actual 28Nov2007 N/A N/A N/A N/A N/A 12DEC2007 N/A N/A 18Jan2007 97,876.00 15Sep2008 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Individual SS N/A N/A N/A N/A N/A N/A $ David 31Dec2008 Actual N/A N/A 11Nov2007 13Nov2007 13Nov2007 N/A N/A N/A N/A 6Sep2007 73,000.00 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Revised Prior Individual CQ N/A N/A N/A N/A N/A N/A $ Gamal horani 31Oct2009 Actual 25June2008 N/A 24June2008 28June2008 28June2008 12Aug2008 18Aug2008 N/A N/A 1Nov2008 22,000.00 Planned N/A N/A N/A N/A N/A N/A N/A 22July2008 N/A N/A N/A Revised Prior Individual CQ N/A N/A N/A N/A N/A N/A 22July2008 $ Hathim Al-Zameki 31Dec2009 Actual 30June2008 N/A 24June2008 29June2008 29June2008 N/A N/A 16Nov2008 3Jan2009 15Dec2008 22,000.00 Planned N/A N/A N/A N/A N/A N/A N/A 22July2008 N/A N/A N/A Revised Prior Individual CQ N/A N/A N/A N/A N/A N/A 22July2008 $ Hathim Al-Zameki 31Dec2009 Actual 30June2008 N/A 24June2008 29June2008 29June2008 N/A N/A 16Nov2008 3Jan2009 15Dec2008 22,000.00 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 20July2009 2,500.00 $ 15Sep2009 Revised Post Firm SS N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Actual 20Sep2008 N/A N/A N/A N/A N/A N/A 17June2009 N/A N/A Planned 10 Oct2009 25Oct2009 N/A 10 Oct2009 N/A N/A N/A 25Nov2009 N/A 10 Dec2009 25Dec2009 $ 40308 Revised Post Firm CQ Actual Planned 10 Oct2009 25Oct2009 N/A 10 Oct2009 N/A N/A N/A 25Nov2009 N/A 10 Dec2009 25Dec2009 $ 40308 Revised Post Firm CQ Actual Planned Revised Post Individual CQ 15Nov2009 28 Nov2009 N/A 5 Dec2009 N/A N/A N/A 10Dec2009 N/A N/A 25Dec2009 $ 39854 Actual Envirnomental Specialist Local PCDP Coordinator - Hodeidah Local PCDP Coordinator - Mukalla Gold mohur Site Potential Study Translation Specialist Urban planning Consultant EIA Consultancy Study for Aden Causeway Resettlement Policy Framwork Ledd Specialist Assest Management Aden 2010 Strategic urban planner Preparation of a notional port strategy for yemen Study and design for Group I Projects -Hodeidah 40 44 41 42 43 Prior 38 Firm QCBS 37 Preparation of Model industrial Estate Program for Yemen's Port Cities The selection process has been cancelled and the assignment will be re-tendered with changing 1,448,100.00 N/A 8April2008 1,081,862.00 489,603.50 49,500.00 35 36 Prior 33 $ $ 5,000.00 Actual Preparation of Model industrial Estate Program for Yemen's Port Cities(Revised 39 6Nov2007 N/A 30Oct2007 4Nov2007 4Nov2007 4Nov2007 6Dec2007 32 Firm QCBS N/A 34
Groupe de la Banque mondiale · Procurement Plan
Republic of Yemen - Port Cities Development Program Project : procurement plan (Vol. 2 of 4) : Procurement plan for consulting services
Voir le document original
Le texte intégral est hébergé par l’organisation qui le publie. lawenc.com indexe les métadonnées et renvoie vers la source officielle.
Texte intégral
Informations clés
Organisation
Groupe de la Banque mondiale
Type de document
Procurement Plan
Source
Banque mondiale