PROCUREMENT PLAN 45026 Second Eastern Indonesia Region Transport Project (EIRTP-2) as of AWP 1 CIVIL WORKS / GOODS BIDDING PROCESS Status: 11-Aug-08 Allocated Amount Cost Program or Design Bidding Document, Incl. Eng. Design Bid Evaluation Report Province/ Inter- EE Procurement Prior / Post Invitation for Bid Opening Contract Contract Amount Nat./Prov./ Supplier/ CP / DP Completion No. Urban Urban / Package No. Name of Link Contract No. Method (USD 1=Rp.8,500) Bids Date Date Signature Date USD / IDR Kab./Kota Contractor Name (days) Kab Review Appr'd /NOL Date Submitted Date Appr'd /NOL Date Submitted Date NOL Date Request Date USD IDR(x1000) Date ICB Prior Review for C.Works PT. Waskita karya, 1 Sulbar/iu ICB 4,773,637 40,575,918 Prior EIB-101 Tapoyo-Karosa-Baras 6-Jan-05 24-Feb-05 6-Jan-05 24-Feb-05 25-Jul-05 6-Sep-05 22-Nov-05 22-Dec-05 15-Feb-06 Rp 45,254,724,777 Nat. Roads 01-053/EIB-101/RB/A/IBRD PT. Pasokorang, PT. 660 7-Dec-07 4744-IND/0206 Duta Graha, JO Ba Baras-Pasangkayu asangkayu- 2 Sulbar/iu lb /i ICB 5,232,977 44,480,304 Prior EIB 102 EIB- 28-Oct-05 11-Nov-05 28-Oct-05 11-Nov-05 15-Dec-05 26-Jan-06 18-Jul-06 28-Jul-06 29-Sep-06 Rp 44,480,304,000 Nat. Roads PT. Daya Mulya Day Mu 02-53/EIB-102/RB/A/IBRD 700 29-Aug-08 Bts.Sulteng Turangga 4744-IND/09/0 3 Sultra/Prov ICB 3,231,384 27,466,761 Prior EIB-107 Tampo-Raha 15-Feb-05 15-Mar-05 15-Feb-05 15-Mar-05 14-Jun-05 28-Jul-05 30-Sep-05 3-Jan-06 31-May-06 Rp 27,466,761,468 Prov. Roads PT Jati Agung 02-56/EIB- 820 28-Aug-08 Arsitama 107/RB/B/4744/0506 Bau Bau-Bana Bungi / S, 4 Sultra/Prov ICB 3,348,813 28,464,911 Prior EIB-108 15-Feb-05 15-Mar-05 15-Feb-05 15-Mar-05 24-Jun-05 8-Aug-05 30-Sep-05 3-Jan-06 8-Jul-06 Rp PT Baita Sari-PT Jati 03-56/EIB- 733 10-Jul-08 Wasaga 28,464,910,892 Prov. Roads Agung Arsitama 108/RB/B/4744/0706 5 Maluku/Prov ICB 4,772,157 40,563,334 Prior EIB-109 Laha-Wakasihu 13-Oct-05 28-Oct-05 13-Oct-05 28-Oct-05 29-Nov-05 19-Jan-06 22-Feb-06 28-Feb-06 24-Aug-06 Rp 40,563,334,000 Prov. Roads 02-60/EIB- PT. Hutama Karya 600 15-Apr-08 109/RB/A/4744/0806 Sub-Total Cost 1 : 21,358,968 181,551,229 Rp 186,230,035,137 NCB Prior Review ( USD 1 million) 1 Maluku/iu NCB 1,532,553 13,026,703 Prior EIBR-100 Bridges ( 8Nos.) 31-Aug-04 3-Jan-05 31-Aug-04 3-Jan-05 28-Apr-05 30-May-05 17-Jun-05 13-Jul-05 17-Nov-05 Rp 13,026,703,404 Nat. Br. 01-60/EIBR-100/ PT Adhi Karya 720 7-Nov-07 BR/A/4744/1105 2 NTT/u NCB 1,635,218 13,899,357 Prior EIPB-101 Kupang 13-Aug-04 12-Nov-04 13-Aug-04 12-Nov-04 1-Mar-05 4-Apr-05 18-May-05 27-May-05 27-Jun-05 Rp 13,899,356,998 Kupang 01-44/EIPB-101/ PT Waskita Karya 240 22-Feb-06 RBPM/A/4744/0605 3 Sulteng/u NCB 1,193,284 10,142,915 Prior EIPB-103 Palu 10-Mar-05 24-Mar-05 28-Mar-05 11-Apr-05 18-Apr-05 23-May-05 14-Jul-05 9-Aug-05 24-Sep-05 Rp 8,452,429,404 Palu PT Triratna K - PT 01-52/EIPB-103/RB/ A/4744- 225 7-May-06 Fajar Raya IND/0905 4 Papua/Kab NCB 2,571,677 21,859,253 Prior EIPB-119 Nuni-Masni 6-Jan-05 14-Jul-05 6-Jun-05 14-Jul-05 29-Jul-05 30-Aug-05 4-Oct-05 25-Oct-05 2-May-06 Rp 21,859,253,000 Mnkwari PT Adhi Karya-PT 01-62/EIPB-119/RB/PM/ 465 10-Aug-07 Delapan E, JO C/4744/0506 Kasuara-Borong Rappoa, 5 Sulsel/Kab NCB 1,706,725 14,507,160 Prior EIPB-120 6-Jan-05 15-Mar-05 6-Jan-05 15-Mar-05 11-May-05 10-Jun-05 18-Aug-05 6-Sep-05 23-Nov-05 Rp 14,507,160,067 B.kumba PT Makassar Indah 01.73/EIPB-120/ 330 19-Oct-06 Sappiri-Gattareng Graha PMRB/C/4744/0805 6 Sulsel/Prov NCB 1,316,923 11,193,843 Prior EIP-103 Arasoe-Watampone 16-Feb-05 28-Feb-05 16-Feb-05 28-Feb-05 28-Apr-05 30-May-05 27-Jul-05 12-Aug-05 21-Nov-05 Rp 11,193,843,046 Prov. Rds PT Bawakaraeng-PT 01-54/EIP-103/ 410 5-Jan-07 Sabar Jaya PM/B/4744/1105 7 Papua/Kab NCB 1,585,164 13,473,890 Prior EIP-127 Usilimo-Bokondini 13-Apr-05 25-Apr-05 13-Apr-05 25-Apr-05 11-May-05 10-Jun-05 30-Jun-05 14-Jul-05 2-May-06 Rp 13,473,890,000 Jayawjya 01-93/EIP.127/ PT Vita Samudra 180 29-Oct-06 PM/C/4744/0506 8 Kalteng/u NCB 2,832,248 24,074,111 Prior EIB-103 Palangkaraya 13-Aug-04 12-Nov-04 13-Aug-04 12-Nov-04 1-Mar-05 4-Apr-05 9-May-05 26-May-05 1-Aug-05 Rp 24,074,110,891 Plgk.Raya PT Prestasi Karya 03-32/EIB-103/ 390 26-Aug-06 Mulia RB/A/4744/0805 Sub-Total Cost 2 : 14,373,792 122,177,233 Rp 120,486,746,810 NCB Prior Review 1st Packet 1 Sulsel/iu NCB 726,909 6,178,722 Prior EIB-100 Pinrang-Polewali 1-Sep-05 29-Sep-05 1-Sep-04 29-Sep-04 28-Apr-05 30-May-05 30-Jun-05 14-Jul-05 29-Nov-05 01-054/EIB-100/ Rp 6,178,722,299 Nat. Rds CV Kilat 240 27-Jul-06 RB/A/4744/1105 Soppeng-Pangkajene PT Bina Konstruksi 2 Sulsel/Prov NCB 1,293,255 10,992,670 Prior EIP-102 8-Sep-04 4-Jan-05 8-Sep-04 4-Jan-05 8-Mar-05 7-Apr-05 1-Jun-05 23-Jun-05 21-Nov-05 01-54/EIP-102/ Rp 10,992,669,964 Prov. Rds 300 17-Sep-06 Sidrap Utama - PT Karya Pare Sejhtera,JO PM/B/4744/1105 3 Kalteng/Kab NCB 221,820 1,885,467 Prior EIPB-107 T Layang-Katambung 4-Jan-05 20-Jan-05 4-Jan-05 20-Jan-05 19-Apr-05 23-May-05 17-Jun-05 13-Jul-05 2-Aug-05 29.32/EIPB-107/ Rp 1,885,467,284 BaritoTim PT Hutama Karya 180 29-Jan-06 PM/C/4744/08.05 Tabalong Mati-Hapalah, 4 Kalsel/Kab NCB 288,571 2,452,853 Prior EIP-113 4-Jan-05 14-Oct-05 27-Sep-05 14-Oct-05 12-Dec-05 12-Jan-06 19-Jun-06 14-Aug-06 4-Sep-06 02-36-EIP- Rp 2,044,044,000 HuluSUt PT Hutama Karya 237 29-Apr-07 Panaitan- 113/PM/C/4744/09.06 5 Sulteng/Kab NCB 1,010,098 8,585,831 Prior EIPB-110 Labean-Manimbaya 11-Feb-05 15-Mar-05 11-Feb-05 15-Mar-05 14-Jun-05 14-Jul-05 29-Aug-05 19-Sep-05 15-Aug-06 PT Karya Baru 01-52/EIPB-110/ Rp 8,585,831,000 Donggala 365 15-Aug-07 Makmur PM/C/4744/0806 Suli-Malakosa, Mertajati- PT Putra J - PT 6 Sulteng/Kab NCB 529,850 4,503,724 Prior EIP-114 11-Feb-05 15-Mar-05 11-Feb-05 15-Mar-05 14-Jun-05 14-Jul-05 31-Aug-05 17-Oct-05 9-Oct-06 03-52/EIP-114/ Rp 4,503,724,000 PrgMout Bunga Cengkeh 240 6-Jun-07 Peore Abadi, JO PM/C/4744/1006 7 Sulsel/Kab NCB 579,615 4,926,729 Prior EIPB-112 Pa'Lingan-Layoa, Pa'Lingan- 7-Jul-05 18-Jul-05 7-Jul-05 18-Jul-05 29-Jul-05 30-Aug-05 18-Oct-05 10-Nov-05 8-Dec-05 PT Citratama T-PT 01-54/EIPB-112/ Rp 4,926,729,276 Bantaeng 240 5-Aug-06 Kaloling Nugraha T, JO PM/C/4744/1205 Damme/Mardekaya-Lantang- 8 Sulsel/Kab NCB 1,034,289 8,791,454 Prior EIPB-113 Cakura-Bantinoto,Bt Kassi- 10-Sep-04 12-Nov-04 10-Sep-04 12-Nov-04 8-Mar-05 7-Apr-05 27-May-05 10-Jun-05 21-Nov-05 PT Karya Mandala Rp 8,791,454,299 Takalar 01-54/EIPB-113/PM/C/ IBRD BRD 377 3-Dec-06 Putra 4744-IND/1105 Bt Kanang Bontopedda-Karumasing, 9 Sulsel/Kab NCB 1,228,513 10,442,362 Prior EIPB-114 Pasir Putih-Batu Belerang, 10-Sep-04 12-Nov-04 10-Sep-04 12-Nov-04 8-Mar-05 7-Apr-05 27-May-05 10-Jun-05 17-Nov-05 PT Usaha Subur Rp 10,442,362,491 Sinjai 01-054/EIPB-114/ PM 300 13-Sep-06 Sejahtera /C/IBRD-4744-IND/1105 Karumasing-Biji Nangka 01-73/EIB- 10 Sulsel/Kab NCB 579,901 4,929,154 Prior EIB-120 Pakalu-Soddange 1-Sep-04 29-Sep-04 1-Sep-04 29-Sep-04 8-Mar-05 7-Apr-05 3-Jun-05 23-Jun-05 17-Nov-05 Rp 4,929,154,375 Maros PT Bumi Karsa 120/RB/C/4744/NOPEMBE 240 15-Jul-06 R 2005 PT Aphasko Utama 11 Sulsel/Kab NCB 736,049 6,256,417 Prior EIB-122 Waempubbu-Pompanua 10-Sep-04 12-Nov-04 10-Sep-04 12-Nov-04 8-Mar-05 7-Apr-05 27-May-05 13-Jun-05 21-Nov-05 Rp 6,256,417,000 Bone Jaya-PT. Citra 07-54/EIB-122/RB/ C/IBRD- 180 20-May-06 Pribumi Teknik 4744-IND/1105 Perkasa.,JO 12 Sulsel/Kab NCB 464,253 3,946,154 Prior EIPB-116 Tikala-Rea 7-Jan-05 18-Apr-05 7-Jan-05 18-Apr-05 11-May-05 10-Jun-05 15-Sep-05 23-Sep-05 18-Nov-05 01-54/EIPB- Rp 3,946,154,000 Tator PT Usaha Subur 379 2-Dec-06 Sejahtera 116/PM/C/4744/1105 Simullu-Palarangan, Camba- 13 Sulbar/Kab NCB 751,520 6,387,922 Prior EIPB-118 Teppo-Palarangan-Kaida- 10-Sep-04 12-Nov-04 10-Sep-04 12-Nov-04 14-Jun-05 14-Jul-05 22-Nov-05 19-Dec-05 16-Jan-06 01-75/EIPB-118/PM- Rp 6,387,921,835 Majene PT Hutama Karya 330 12-Dec-06 Tinambung, Ambawe- RB/C/4744/0106 Rawang 14 Papua/Kab NCB 656,882 5,583,495 Prior EIP-129 Korem-Yenggarbun 26-Aug-04 11-Nov-04 26-Aug-04 11-Nov-04 8-Mar-05 7-Apr-05 17-Jun-05 13-Jul-05 10-May-06 PT Artamakmur 01-62/EIP-129/ Rp 5,583,495,000 Biak Nmfr 240 5-Jan-07 Permai PM/C/4744/0506 15 Papua/Kab NCB 398,615 3,388,230 Prior EIB-127 Muai-Musatfak 31-Aug-04 3-Jan-05 31-Aug-04 3-Jan-05 11-May-05 10-Jun-05 30-Jun-05 14-Jul-05 2-May-06 48,1/PRO-IBRD-EIB- Rp 3,388,230,000 Jayawijaya CV Ataka Serui 180 29-Oct-06 127/2006 Sub-Total Cost 3 : 10,500,139 89,251,186 Rp 88,842,376,822 AWP-1 Page 1 PROCUREMENT PLAN Second Eastern Indonesia Region Transport Project (EIRTP-2) as of AWP 1 CIVIL WORKS / GOODS BIDDING PROCESS Status: 11-Aug-08 Allocated Amount Cost Program or Design Bidding Document, Incl. Eng. Design Bid Evaluation Report Province/ Inter- EE Procurement Prior / Post Invitation for Bid Opening Contract Contract Amount Nat./Prov./ Supplier/ CP / DP Completion No. Urban Urban / Package No. Name of Link Contract No. Method (USD 1=Rp.8,500) Bids Date Date Signature Date USD / IDR Kab./Kota Contractor Name (days) Kab Review Appr'd /NOL Date Submitted Date Appr'd /NOL Date Submitted Date NOL Date Request Date USD IDR(x1000) Date NCB Post Review 2nd Packet... etc 1 Kalteng/Kab NCB 118,988 1,011,399 Post EIP-110 Ampah-Awang 26-Aug-04 4-Jan-05 26-Aug-04 4-Jan-05 8-Mar-05 8-Apr-05 16-May-05 27-Jul-05 15-Aug-05 30-32/EIP-110/ Rp 1,011,398,545 BaritoTim PT.Hutama Karya 180 11-Feb-06 PM/C/4744/08.05 2 Sulteng/Kab NCB 247,346 2,102,444 Post EIP-116 Taopa-Sibatang 11-Feb-05 15-Mar-05 11-Feb-05 15-Mar-05 14-Jun-05 14-Jul-05 29-Jul-05 15-Aug-06 22-Aug-06 PT. Makmur 01-52/EIP- Rp 2,102,444,000 PrgMout 255 4-May-07 Sulteng Raya, JO 116/PM/C/4744/0806 Sp. Allu-Sinoa, Panaikang- PT. Ctratama Timurindo- 3 Sulsel/Kab NCB 561,387 4,771,791 Post EIP-118 6-Jan-05 15-Mar-05 6-Jan-05 15-Mar-05 29-Jul-05 30-Aug-05 9-Dec-05 10-Dec-05 19-Dec-05 02-54/EIP-118/ Rp 4,771,791,000 Bantaeng PT. Nugraha Tanamal, 240 16-Aug-06 Maroa JO RB/C/4744/1205 Kassi-Amma'Rang P- 4 Sulsel/Kab NCB 412,998 3,510,480 Post EIB-121 1-Sep-04 30-Sep-04 1-Sep-04 30-Sep-04 8-Mar-05 7-Apr-05 29-Jun-05 15-Nov-05 02-73/EIB- Rp 3,510,479,768 Maros PT. Putrajaya-PT 240 13-Jul-06 Sabantang Patriot J. Pratama, JO 121/RB/C/4744/1105 5 Sulsel/Kab NCB 546,121 4,642,027 Post EIB-123 Lapeccang-Pattiro Bajo 10-Sep-04 12-Nov-04 10-Sep-04 12-Nov-04 8-Mar-05 7-Apr-05 4-May-05 21-Nov-05 Rp 4,642,027,211 Bone PT.Sabar Jaya, CV.Karya 08-54/EIB-123/RB/C/IBRD 4744- 180 20-May-06 Subur Utama,JO IND/1105 6 Sulsel/Kab NCB 301,632 2,563,869 Post EIP-121 Rura-Tomabng Kalua 6-Jan-05 15-Mar-05 6-Jan-05 15-Mar-05 11-May-05 10-Jun-05 2-Aug-05 30-Dec-05 PT. Sabar Jaya 02-54/EIP-121/ Rp 2,563,869,000 Tator 180 28-Jun-06 Pratama PM/C/4744/1205 7 Sulsel/Kab NCB 219,877 1,868,952 Post EIP-122 Makula-Batualu 6-Jan-05 15-Mar-05 6-Jan-05 15-Mar-05 11-May-05 10-Jun-05 2-Aug-05 30-Dec-05 PT. Sabar Jaya 02-54/EIP-122/ Rp 1,868,952,000 Tator 180 28-Jun-06 Pratama PM/C/4744/1205 Sub-Total Cost 4 : 2,408,348 20,470,962 Rp 20,470,961,524 ICB for Goods Packets 1 Jakarta ICB 3,411,111 28,994,447 Post EIG-1 4-Nov-04 9-Nov-04 22-Nov-04 5-Jan-05 17-Feb-05 3-Mar-05 4-May-05 PT Waagner Biro 01-20/EIG- Rp 28,994,446,800 Bridge Truss Indonesia 1/GD/A/4744/0505 Rp 2,823,236,031 Construction Kanto Bussan Kaisha, 2 Jakarta ICB 1,693,492 14,394,680 Post EIG-2 24-Feb-06 18-May-06 12-Jun-06 1-Aug-06 6-Nov-06 7-Nov-06 27-Nov-06 Material Lab. 03-20/EIG-2 GBP 396,106 Ltd, Panairsan Testing /GD/A/4744/1106 USD 202,588 Pratama, JO Equipment IT Equip. for 3 Jakarta ICB 591,000 5,023,500 Post EIG-3 16-May-06 27-Jul-06 3-Aug-06 15-Sep-06 19-Oct-06 12-Feb-07 26-Mar-07 PT. Wira Eka 04-20/EIG-3 Rp 4,726,293,000 PMU, BIPRAM, and BPJT Bhakti /GD/A/4744/0307 5,695,603 48,412,627 CP = Construction Period Total Cost : 54,336,851 461,863,235 DP = Delivery Period ICB Prior Review for C.Works 04/34/EIB- 1 Sulbar/Prov. ICB 4,773,350 40,573,472 Prior EIB-106 Polewali-Tabone 22-Mar-07 04-Apr-07 22-Mar-07 04-Apr-07 23-Apr-07 06-Jun-07 24-Aug-07 11-Sep-07 09-Oct-07 Rp 40,573,472,153 Prov. Rds PT. Istaka Karya 520 12-Mar-09 106/RB/B/4774/1007 Rp 73,763,395.000 (Rp PY Nindya Simp. Pelita Jaya- 04-60/EIB- 2 Maluku/Prov. ICB 6,890,588 58,570,000 Prior EIB-110 05-Sep-07 21-Sep-07 05-Sep-07 21-Sep-07 24-Oct-07 06-Dec-07 12-Feb-08 30-May-08 04-Jul-08 58,570,000,000 from Loan- Prov. Rds Karya, PT 500 16-Nov-09 Taniwel APBD & Rp 15,193,395,000 fr Brantas A, PT 110/RB/B/4744/0708 APBD-Prov. Budget FY 08) Anugrah K, JO Sub-Total Cost 1 : 11,663,938 99,143,472 Rp 40,573,472,153 NCB Prior Review ( USD 1 million) Nualinu-Hangalande, PT. Nindya 05-0824/EIB- 1 NTT/Kab NCB 2,258,747 19,199,345 Prior EIB-115 19-Oct-06 03-Nov-06 19-Oct-06 03-Nov-06 19-Dec-06 04-Jan-07 07-Mar-07 13-Mar-07 23-Apr-07 Rp 19,199,345,355 Ende 420 16-Jun-08 Nduaria-Warundari Karya 115/RB/C/4744/0207 PT. Waskita 01-23/EIPB- 2 NTB/u NCB 1,970,589 16,750,007 Prior EIPB-100 Jl. Jend. Sudirman, Jl. Adi S 30-Nov-06 22-Jan-07 30-Nov-06 22-Jan-07 01-Feb-07 06-Mar-07 14-May-17 23-May-07 11-Jun-07 Rp 15,660,578,272 Mataram 360 5-Jun-08 karya 100/RB/A/4744/0607 3 Maluku/Prov. NCB 1,744,776 14,830,597 Prior EIP-104 Piru-Simp.Pelita Jaya 21-Sep-06 29-Sep-06 21-Sep-06 29-Sep-06 19-Oct-06 23-Nov-06 21-Dec-06 04-Jan-06 01-Feb-07 Rp 14,635,956,000 Prov. Rds PT Anugerah Karya 01.06/EIP-104/ 590 13-Sep-08 Agra Sentosa PM/B/4744/0207 4 Papua/u NCB 1,568,729 13,334,193 Prior EIP-100 Jayapura 05-Mar-08 01-Apr-08 05-Mar-08 01-Apr-08 12-May-08 11-Jun-08 23-Jul-08 30-Jul-08 09-Oct-08 Jayapura 240 6-Jun-09 5 Papua/Kab NCB 1,637,674 13,920,225 Prior EIB-129 Kontiunai-Ambaidiru 08-May-08 19-May-08 08-May-08 19-May-08 02-Jun-08 02-Jul-08 13-Aug-08 20-Aug-08 30-Oct-08 Yapen Wrp 240 27-Jun-09 6 NTT.Kab NCB 2,115,953 17,985,602 Prior EIB-108G Bitauni-Manufui 19-Oct-06 03-Nov-06 19-Oct-06 03-Nov-06 16-Nov-06 19-Dec-06 07-Mar-07 05-Apr-07 28-May-07 Rp 17,985,602,316 PT. Anugrah Karya 01-24-EIB- TimTghUt 420 21-Jul-08 Agra Sentosa 108G/RB/C/4744/0507 7 Sulbar/Kab NCB 2,352,941 20,000,000 Prior EIP-126G Kuo-Tommo 28-Dec-06 05-Jan-07 28-Dec-06 05-Jan-07 30-Jan-07 01-Mar-07 03-May-07 15-May-07 14-Jun-07 Rp 19,865,000,000 Mamuju PT. 02-54/EIP- 480 6-Oct-08 PASSOKORANG 126G/RB/C/4744/0407 8 NTB/Kab NCB 2,230,771 18,961,550 Prior EIP-107G Dena-Campa 11-Dec-06 19-Dec-06 11-Dec-06 19-Dec-06 01-Feb-07 06-Mar-07 14-May-07 25-May-07 15-Jun-07 Rp 18,865,089,684 Bima PT. LANCAR 04-23/EIP- 365 14-Jun-08 SEJATI, JO 107G/PM/C/4744/0607 PT. WASKITA 9 NTB/Kab NCB 2,414,700 20,524,950 Prior Mt Gamang-Janapiria, 02-23/EIP- EIP-105G 11-Dec-06 19-Dec-06 11-Dec-06 19-Dec-06 01-Feb-07 06-Mar-07 14-May-07 25-May-07 30-Jun-07 Rp 22,043,978,000 Lmbk Tgh KARYA 495 6-Nov-08 Mangkung-Selong Belanak 105G/PM/C/4744/0607 PERSERO 10 Irjabar/u NCB 2,117,191 17,996,126 Prior EIP-101 Sorong 18-Apr-08 24-Apr-08 18-Apr-08 24-Apr-08 26-May-08 01-Jul-08 12-Aug-08 19-Aug-08 29-Oct-08 240 26-Jun-09 Despot-Modo, Tayadun- 11 Sulteng/Kab NCB 1,285,377 10,925,701 Prior EIB-118 21-Apr-08 02-May-08 21-Apr-08 02-May-08 19-May-08 18-Jun-08 30-Jul-08 06-Aug-08 16-Oct-08 Buol Poongan Sub-Total Cost 2 : 21,697,447 184,428,297 Rp 128,255,549,627 AWP-1 Page 2 PROCUREMENT PLAN Second Eastern Indonesia Region Transport Project (EIRTP-2) as of AWP 1 CIVIL WORKS / GOODS BIDDING PROCESS Status: 11-Aug-08 Allocated Amount Cost Program or Design Bidding Document, Incl. Eng. Design Bid Evaluation Report Province/ Inter- EE Procurement Prior / Post Invitation for Bid Opening Contract Contract Amount Nat./Prov./ Supplier/ CP / DP Completion No. Urban Urban / Package No. Name of Link Contract No. Method (USD 1=Rp.8,500) Bids Date Date Signature Date USD / IDR Kab./Kota Contractor Name (days) Kab Review Appr'd /NOL Date Submitted Date Appr'd /NOL Date Submitted Date NOL Date Request Date USD IDR(x1000) Date NCB Prior Review 1st Package Adu-Rasabou, Sakalo- PT. Rangga 1 NTB/Kab NCB 1,611,108 13,694,415 Prior EIP-106G 11-Dec-06 19-Dec-06 11-Dec-06 19-Dec-06 01-Feb-07 06-Mar-07 23-May-07 30-May-07 15-Jun-07 Rp 14,757,945,990 Dompu 03-23/EIP- 300 10-Apr-08 Saneo Ekapratama 106G/PM/C/4744/0607 2 NTT/Kab NCB 1,624,547 13,808,646 Prior EIPB-104 Bukapiting-Apui 28-Sep-07 10-Oct-07 28-Sep-07 10-Oct-07 25-Oct-07 28-Nov-07 04-Jan-08 18-Jan-08 06-Feb-08 Rp 13,652,199,000 Alor PT. Adhi Karya 01-0524/EIPB- 360 31-Jan-09 104/RBPM/C/4744/0208 3 Kalteng/Kab NCB 2,281,165 19,389,900 Prior EIPB-105G K Kapuas-Mandomai 09-Nov-07 21-Nov-07 09-Nov-07 21-Nov-07 17-Dec-07 17-Jan-08 21-Jul-08 28-Jul-08 27-Aug-08 Rp 20,928,727,251 Kapuas PT Mahir Jaya 365 27-Aug-09 Padang Loang-Dongi- PT. Karya Pare 01-1917/EIP-115G/PM- 4 Sulsel/Kab NCB 1,464,234 12,445,985 Prior EIP-115G 20-Apr-07 04-May-07 20-Apr-07 04-May-07 25-May-07 26-Jun-07 31-Aug-07 14-Sep-07 03-Oct-07 Rp 12,284,694,867 Sidrap 240 30-May-08 Tannutedong Sejahtera C/4744/1007 5 Sultra/u NCB 727,116 6,180,485 Prior EIPB-102 Kendari 17-Dec-07 3-Jan-08 17-Dec-07 3-Jan-08 3-Mar-08 10-Apr-08 22-May-08 29-May-08 08-Aug-08 Kendari 150 5-Jan-09 PT. Torea Fak- 6 Irjabar/Kab NCB 1,058,658 8,998,591 Prior EIP-128 Hurimber-Kinam 29-Sep-06 10-Oct-06 29-Sep-06 10-Oct-06 10-Nov-06 13-Dec-06 25-Jan-07 30-Jan-07 07-Feb-07 Rp 7,844,401,000 Fakfak 06-62/EIP-128/ 288 22-Nov-07 fak Indah PM/C/4744/0207 7 Sulteng/Kab NCB 1,097,533 9,329,032 Prior EIPB-111 Buatan-Bilo, Tambun-Bilo 21-Apr-08 05-May-08 21-Apr-08 05-May-08 13-May-08 11-Jun-08 23-Jul-08 30-Jul-08 09-Oct-08 Toli-Toli Sub-Total Cost 3 : 9,864,359 83,847,054 NCB Post Review 2nd Packet... etc 1 Sulteng/Kab NCB 183,622 1,560,786 Post EIP-117G Sp.Kasimbar- Dusun III 5-Oct-07 29-Oct-07 5-Oct-07 29-Oct-07 25-Feb-07 1-Apr-08 29-Apr-08 13-May-08 30-Jul-08 Prg. Moutong 180 26-Jan-09 2 Sulbar/Kab NCB 619,009 5,261,576 Post EIP-123G Tanete-Tande-Luttang, 23-Jan-08 31-Jan-08 23-Jan-08 31-Jan-08 29-Feb-08 1-Apr-08 2-Jul-08 25-Jul-08 08-Aug-08 Rp 8,479,889,817 Majene PT Lumpue Indah 240 5-Apr-09 Tanete-Galung 3 Sulteng/Kab NCB 642,353 5,460,000 Post EIB-117 Gimpu-Peana 6-May-08 30-May-08 6-May-08 30-May-08 07-Jun-08 07-Jul-08 04-Aug-08 18-Aug-08 04-Nov-08 Donggala 270 1-Aug-09 1,444,984 12,282,363 NCB for Goods Package EIG-4 Lot A 02-20/EIG- 1 Jakarta NCB 195,000 1,657,500 Post N.A N.A N.A N.A 30-Jun-06 1-Aug-06 15-Sep-06 9-Oct-06 3-Nov-06 Rp 1,156,870,000 PT. Karya Agung 15 18-Nov-06 (Lot A) contract Alexander Motor 4/GD/A/4744/1106 EIG-4 Lot B 06-20/EIG- N.A N.A N.A N.A 21-Feb-07 22-Mar-07 21-May-07 Rp 798,996,000 PT. Karya Agung 15 5-Jun-07 (Lot B) contract Alexander Motor 4/GD/A/4744/507 195,000 1,657,500 Rp 1,955,866,000 CP = Construction Period Total Cost : 44,865,728 381,358,686 All Works and Goods Packets apply Post Qualification and Unit Price Contract methods Rp 170,784,887,780 DP = Delivery Period Note Post Review < USD 1 million Prior Review > USD 1 million Date of process already complete Expected date to complete Date overdue For Prior Review Packages : 1. From bid opening to request for World Bank no objection max 6 weeks 2. From bid opening to award max 120 days For Post Review Packages : 1. From bid opening to request for Bina Program approval max 4 weeks 2. From bid opening to award max 120 days AWP-1 Page 3 PROCUREMENT PLAN Second Eastern Indonesia Region Transport Project (EIRTP-2) as of AWP 2 & 3 11-Aug-08 CIVIL WORKS BIDDING PROCESS Allocated Amount Cost Program or EE Design Bidding Document Incl. Eng. Bid Evaluation Report Contract Amount USD / Province/ Inter- Procurement Prior / Post Design Invitation for Bid Opening Contract IDR Nat./Prov./ Supplier/ Contractor CP/DP Completion No. Urban Urban / Package No. Name of Link Contract No. Method 1 USD = IDR 9,100 Review Submitted Appr'd /NOL Submitted Bids Date Date Appr'd /NOL Signature Date Kab./Kota Name (days) Kab NOL Date Request Date Original Date USD IDR(x1000) Date Date Date Date ICB Prior Review for C.Works 1 Sulbar/iu ICB 9,832,844 89,478,882 Prior EIB-157 Kaluku-Topoyo, cs 5-Dec-07 8-Jan-08 5-Dec-07 8-Jan-08 29-Feb-08 16-May-08 27-Jun-08 4-Jul-08 13-Sep-08 Nat. Roads 390 8-Oct-09 01-30/EIPB- 2 Kalbar/Prov ICB 5,015,418 45,640,300 Prior EIPB-139 A Singkawang-Sambas 20-Aug-07 3-Sep-07 20-Aug-07 3-Sep-07 14-Dec-07 5-Feb-08 15-May-08 23-May-08 19-Jun-08 Rp 40,223,003,000 Prov. Road PT Mahir Jaya 365 19-Jun-09 139A/RB/B/4744/0608 01-30/EIPB- 3 Kalbar/Prov ICB 4,279,198 38,940,700 Prior EIPB-139 B Tebas-Sambas 20-Aug-07 3-Sep-07 20-Aug-07 3-Sep-07 14-Dec-07 5-Feb-08 15-May-08 23-May-08 19-Jun-08 Rp 34,420,958,000 Prov. Road PT Bangun Cipta 365 19-Jun-09 139B/RB/B/4744/0608 Sub-Total Cost 1 : 19,127,460 174,059,882 NCB Prior Review ( USD 1 million) 1 Sulsel/IU NCB 954,815 8,688,820 Prior EIP-130 Maros-Bcd. Bone Barat 11-Oct-07 25-Oct-07 11-Oct-07 25-Oct-07 24-Apr-08 24-May-08 5-Jul-08 12-Jul-08 21-Sep-08 Nat. Roads 150 18-Feb-09 Tarumpake-Bts.Luwu 2 Sulsel/IU NCB 1,570,054 14,287,490 Prior EIB-133 11-Oct-07 25-Oct-07 11-Oct-07 25-Oct-07 24-Apr-08 24-May-08 5-Jul-08 12-Jul-08 21-Sep-08 Nat. Roads 210 19-Apr-09 Selatan PT Modern Widya 02-60/EIB- 3 Maluku/IU NCB 2,679,863 24,386,755 Prior EIB-134 Mako-Namrole 4-Jan-08 23-Jan-08 4-Jan-08 23-Jan-08 8-Feb-08 13-Mar-08 6-Jun-08 16-Jun-08 3-Jul-08 Rp 30,340,188,000 Nat. Roads 360 28-Jun-09 Technical 134/RB/A/4744/0708 01-52/EIB- 4 Sulteng/Prov NCB 2,042,658 18,588,184 Prior EIB-137 Balingara-Bunta 29-Sep-06 3-Oct-06 29-Sep-06 3-Oct-06 30-Jan-07 6-Mar-07 16-Jul-07 25-Jul-07 15-Aug-07 Rp 13,799,708,901 Prov. Road PT Bumi Karsa 420 8-Oct-08 137/RB/B/4744/0807 PT Yala Persada 5 Maluku/Prov NCB 2,158,962 19,646,553 Prior EIP-132 Langgur-Danar 28-Sep-07 24-Oct-07 28-Sep-07 24-Oct-07 29-Jan-08 4-Mar-08 17-Jun-08 3-Jul-08 2-Aug-08 Rp 22,200,570,000 Prov. Road 365 2-Aug-09 Angkasa 03-60/EIBR- 6 Maluku/Prov NCB 1,626,363 14,799,902 Prior EIBR-106 Morela-Liang & Bridges 28-Sep-07 24-Oct-07 28-Sep-07 24-Oct-07 29-Jan-08 4-Mar-08 22-May-08 30-May-08 20-Jun-08 Rp 16,203,982,000 Prov. Road PT Nindya Karya 300 16-Apr-09 106/BR/B/4744/0608 Rp 21,925,073,000 (Rp 01-33/EIB- 7 Irjabar/Prov NCB 2,224,780 20,245,496 18,000,000,000 from Loan- Prior EIB-141 Sorong-Seget 29-Sep-06 5-Oct-06 29-Sep-06 5-Oct-06 6-Aug-07 6-Sep-07 5-Nov-07 16-Nov-07 26-Nov-07 Prov. Road PT Brantas Abipraya 360 20-Nov-08 APBD & Rp 3,925,073,000 fr 141/RB/B/4744/1107 APBD-Prov. Budget FY 08) 8 NTB/U NCB 1,773,264 16,136,702 Prior EIPB-123 Jl. Sutami, etc. 25-Oct-07 1-Nov-07 25-Oct-07 1-Nov-07 5-Dec-07 14-Jan-08 31-Mar-08 17-Apr-08 5-May-08 Rp 18,296,507,621 Nat. Roads PT Adhi Karya, JO 05-23/EIPB- 180 1-Nov-08 123/RB/A/4744/0508 PT Tamako Raya 9 Kalteng/Kab NCB 1,246,857 11,346,400 Prior EIB-159 Ampah-Awang 9-Nov-07 21-Nov-07 9-Nov-07 21-Nov-07 29-Feb-08 1-Apr-08 9-Jun-08 16-Jun-08 30-Jul-08 Rp 10,102,100,000 Barito Timur 330 25-Jun-09 Perdana 10 NTB/Kab NCB 1,354,790 12,328,586 Prior EIPB-124 Sp.Latonda-SP.Kadindi 7-Nov-07 16-Nov-07 7-Nov-07 16-Nov-07 21-Jan-08 20-Feb-08 2-Apr-08 9-Apr-08 19-Jun-08 Dompu 270 16-Mar-09 11 Sulteng/Kab NCB 1,035,465 9,422,730 Prior EIPB-133 Babatona-Pem. Trans 11-Oct-07 25-Oct-07 11-Oct-07 25-Oct-07 14-May-08 13-Jun-08 25-Jul-08 1-Aug-08 11-Oct-08 Donggala 360 6-Oct-09 12 Sulteng/Kab NCB 1,388,684 12,637,027 Prior EIB-143 Air Terang-Modo 11-Oct-07 25-Oct-07 11-Oct-07 25-Oct-07 23-Apr-08 5-Jun-08 17-Jul-08 24-Jul-08 3-Oct-08 Buol 360 28-Sep-09 Parigi PT Mahir Jaya 13 Sulteng/Kab NCB 1,560,518 14,200,718 Prior EIP-136 Suli-Puluksari 14-Nov-07 27-Nov-07 14-Nov-07 27-Nov-07 25-Feb-08 1-Apr-08 12-May-08 22-May-08 3-Jul-08 Rp 13,114,180,000 01-52/EIP- 360 28-Jun-09 Moutong Makahakam Jaya 136/PM/C/4744/0708 14 Sulsel/Kab NCB 1,038,893 9,453,923 Prior EIB-145 Pamanjengan-Btg.Gajah 7-Nov-07 16-Nov-07 7-Nov-07 16-Nov-07 10-Apr-08 14-May-08 25-Jun-08 2-Jul-08 11-Sep-08 Maros 270 8-Jun-09 15 Papua/Kab NCB 1,241,889 11,301,193 Prior EIB-148 Sp.II Legari-Sp.IV Legari 18-Apr-08 24-Apr-08 18-Apr-08 24-Apr-08 2-May-08 12-Jun-08 24-Jul-08 31-Jul-08 10-Oct-08 Nabire 240 7-Jun-09 PT Modern Widya 16 Papua/Kab NCB 1,748,313 15,909,651 Prior EIB-155 Kenyapa-Waghete 5-Mar-08 1-Apr-08 5-Mar-08 1-Apr-08 16-May-08 17-Jun-08 25-Jul-08 1-Aug-08 15-Oct-08 Rp 18,294,965,000 Paniai 300 11-Aug-09 Technical 17 Irjabar/Kab NCB 1,108,963 10,091,567 Prior EIB-152 Rangkedak-Tetar 8-May-08 19-May-08 8-May-08 19-May-08 23-May-08 24-Jun-08 6-Aug-08 13-Aug-08 22-Oct-08 Rp 9,540,389,000 Fakfak PT Nikita Raya 240 19-Jun-09 Sub-Total Cost 2 : 26,755,131 243,471,696 NCB Prior Review 1st Packet PT. Gaya Bangun 01-28/EIP- 1 Mal Utr/U NCB 830,330 7,556,000 Prior EIP-131 Jl. Merdeka, etc. 31-Aug-07 14-Sep-07 31-Aug-07 14-Sep-07 12-Oct-07 28-Nov-07 23-Jan-08 12-Feb-08 6-Mar-08 Rp 7,545,844,405 Nat. Roads 180 2-Sep-08 Prajatama, JO 131/PM/C/4744/0308 Sub-Total Cost 3 : 830,330 7,556,000 NCB Post Review 2nd Packet... etc 1 Sulteng/Prov NCB 513,464 4,672,525 Post EIBR-102 Korompodi 5-Oct-07 29-Oct-07 5-Oct-07 29-Oct-07 5-Dec-07 17-Jan-08 14-Feb-08 28-Feb-08 16-May-08 Prov. Roads 240 11-Jan-09 2 Sultra/Prov NCB 318,226 2,895,854 Post EIBR-105 S. Aepodu 12-Nov-07 28-Dec-07 12-Nov-07 28-Dec-07 16-Jun-08 18-Jul-08 15-Aug-08 29-Aug-08 15-Nov-08 Prov. Roads 300 11-Sep-09 3 Sulsel/U NCB 659,375 6,000,311 Post EIB-135 Jl. Sudirman 1-Aug-07 29-Oct-07 1-Aug-07 29-Oct-07 24-Apr-08 24-May-08 21-Jun-08 5-Jul-08 21-Sep-08 Nat. Roads 240 19-May-09 PT Karya Bumi 05-60/EIP- 4 Malut/U NCB 305,275 2,778,000 Post EIP-139 Jl. Ahmad Yani, etc. 31-Aug-07 14-Sep-07 31-Aug-07 14-Sep-07 11-Oct-07 29-Nov-07 23-Jan-08 11-Mar-08 7-Apr-08 Rp 3,246,842,000 Nat. Roads 60 6-Jun-08 Nasional Perkasa 139/PM/A/4744/04.08 5 Kalsel/Kab NCB 210,780 1,918,100 Post EIPB-132 Bungin-Mr. Jambu, etc. 1-Aug-07 14-Nov-07 1-Aug-07 14-Nov-07 12-May-08 16-Jun-08 14-Jul-08 28-Jul-08 14-Oct-08 Balangan 160 23-Mar-09 Hulu Sungai 6 Kalsel/Kab NCB 469,176 4,269,500 Post EIPB-131 Tangkawang-Harus 30-Jul-07 14-Nov-07 30-Jul-07 14-Nov-07 12-Apr-08 29-May-08 26-Jun-08 10-Jul-08 26-Sep-08 210 24-Apr-09 Utara 7 NTB/Kab NCB 155,481 1,414,877 Post EIP-140 Rato - Mangge 5-Oct-07 29-Oct-08 5-Oct-07 29-Oct-08 9-May-08 12-Jun-08 10-Jul-08 24-Jul-08 10-Oct-08 Bima 120 7-Feb-09 8 Sulteng/Kab NCB 837,830 7,624,250 Post EIB-142 Bilo-Lampasio 5-Oct-07 29-Oct-07 5-Oct-07 29-Oct-07 10-May-08 9-Jun-08 7-Jul-08 21-Jul-08 7-Oct-08 Toli-toli 300 3-Aug-09 9 Sulsel/Kab NCB 858,573 7,813,012 Post EIBR-104 Lobu Bridge 5-Oct-07 29-Oct-07 5-Oct-07 29-Oct-07 5-Dec-07 17-Jan-08 14-Feb-08 28-Feb-08 16-May-08 Prov. Roads 360 11-May-09 PT Purnama Karya - PT 10 Sulsel/Kab NCB 705,263 6,417,893 Post EIB-161 Palampang-Palangisang 1-Aug-07 29-Oct-07 1-Aug-07 29-Oct-07 24-Dec-07 31-Jan-08 2-May-08 27-May-08 30-May-08 Rp 6,293,093,912.72 Bulukumba 250 4-Feb-09 Agung Perdana 11 Sulsel/Kab NCB 245,045 2,229,910 Post EIB-144 Morowa-Talakaya 9-Aug-07 30-Jan-08 9-Aug-07 30-Jan-08 15-Feb-08 28-Mar-08 25-Apr-08 9-May-08 26-Jul-08 Bantaeng 150 23-Dec-08 12 Sulsel/Kab NCB 624,080 5,679,131 Post EIP-138 Korong-Bua, etc. 5-Oct-07 29-Oct-07 5-Oct-07 29-Oct-07 23-Jan-08 26-Feb-08 3-Jul-08 25-Jul-08 8-Aug-08 Rp 5,629,904,705 Sinjai PT Tri Star Mandiri, JO 150 5-Jan-09 PT Karya Subur 13 Sulsel/Kab NCB 861,910 7,843,383 Post EIB-146 Lapecang-Lonrong 9-Aug-07 29-Oct-07 9-Aug-07 29-Oct-07 23-Jan-08 26-Feb-08 30-May-08 17-Jun-08 25-Jun-08 Rp 9,411,600,258.97 Bone 270 22-Mar-09 Teknik, JO PT Bina Konstruksi 14 Sulsel/Kab NCB 537,075 4,887,380 Post EIB-147 Cipotakari-Anabanae, etc. 5-Oct-07 29-Oct-07 5-Oct-07 29-Oct-07 23-Jan-08 26-Feb-08 12-May-08 30-May-08 25-Jun-08 Rp 6,081,349,986 Sidenreng 210 21-Jan-09 Utama Barana-Pangli Pallawa, PT Usaha Subur 15 Sulsel/Kab NCB 581,654 5,293,053 Post EIPB-135 29-Oct-07 30-Jan-08 29-Oct-07 30-Jan-08 15-Feb-08 28-Mar-08 26-Jun-08 25-Jul-08 8-Aug-08 Rp 5,280,859,919 Tana Toraja 210 6-Mar-09 etc. Sejahtera 16 Papua/Kab NCB 881,170 8,018,648 Post EIB-162 Nuni-Masni 7-Aug-07 11-Jun-08 7-Aug-07 11-Jun-08 7-Jul-08 6-Aug-08 3-Sep-08 17-Sep-08 4-Dec-08 Manokwari 240 1-Aug-09 Sub-Total Cost 4 : 8,764,377 79,755,827 CP = Construction Period Total Cost : 55,477,297 504,843,405 All Works and Goods Packets apply Post Qualification and Unit Price Contract methods DP = Delivery Period Page 1 DEIRTP2 AWP1-2-3 for ProcPlan Aug 08 - actual modified PROCUREMENT PLAN Second Eastern Indonesia Region Transport Project (EIRTP-2) as of AWP 2 & 3 11-Aug-08 CIVIL WORKS BIDDING PROCESS Allocated Amount Cost Program or EE Design Bidding Document Incl. Eng. Bid Evaluation Report Contract Amount USD / Province/ Inter- Procurement Prior / Post Design Invitation for Bid Opening Contract IDR Nat./Prov./ Supplier/ Contractor CP/DP Completion No. Urban Urban / Package No. Name of Link Contract No. Method 1 USD = IDR 9,100 Review Submitted Appr'd /NOL Submitted Bids Date Date Appr'd /NOL Signature Date Kab./Kota Name (days) Kab NOL Date Request Date Original Date USD IDR(x1000) Date Date Date Date ICB Prior Review for C.Works PT Strada 1 Kalbar/IU ICB 3,400,055 30,940,500 Prior EIB-164 G Sei Duri-Singkawang 20-Aug-07 3-Sep-07 20-Aug-07 3-Sep-07 14-Dec-07 14-Feb-08 17-Jun-08 24-Jun-08 24-Jul-08 Rp 36,871,158,000.00 Nat. Road 360 19-Jul-09 Multiperkasa Sampit-Samuda, Samuda- 2 Kalteng/Prov NCB 4,832,088 43,972,000 Prior EIB-172 G 9-Nov-07 21-Nov-07 9-Nov-07 21-Nov-07 25-Feb-08 22-May-08 3-Jul-08 10-Jul-08 19-Sep-08 Prov. Roads 365 19-Sep-09 Ujungpandaran 01-24/EIPB- 3 NTB/IU ICB 7,748,876 70,514,775 Prior EIPB-141 Niki Niki-Noelmuti, etc. 11-Oct-07 29-Oct-07 11-Oct-07 29-Oct-07 14-Nov-07 7-Jan-08 4-Mar-08 8-Apr-08 10-Jun-08 Rp 69,555,069,803.37 Nat. Road PT Waskita Karya 365 10-Jun-09 141/RPB/4744/0608 4 Sulbar/IU ICB 4,871,334 44,329,135 Prior EIB-165 Topoyo-Karosa, etc. 5-Dec-07 17-Dec-07 5-Dec-07 17-Dec-07 29-Feb-08 16-May-08 27-Jun-08 4-Jul-08 13-Sep-08 Nat. Road 390 8-Oct-09 5 Sulbar/IU ICB 5,757,042 52,389,082 Prior EIPB-142 Baras-Pasangkayu, etc. 5-Dec-07 17-Dec-07 5-Dec-07 17-Dec-07 29-Feb-08 16-May-08 27-Jun-08 4-Jul-08 13-Sep-08 Nat. Road 390 8-Oct-09 6 Sulsel/IU ICB 8,189,365 74,523,225 Prior EIB-166 Wotu-Masamba 25-Oct-07 2-Nov-07 25-Oct-07 2-Nov-07 24-Apr-08 5-Jun-08 17-Jul-08 24-Jul-08 3-Oct-08 Nat. Road 420 27-Nov-09 Makale-Bts. Cabdin Luwu 7 Sulsel/IU ICB 5,219,512 47,497,558 Prior EIB-167 14-Nov-07 16-Apr-08 14-Nov-07 16-Apr-08 24-Apr-08 26-May-08 7-Jul-08 14-Jul-08 23-Sep-08 Nat. Road 390 18-Oct-09 Selatan 8 Sulsel/IU ICB 4,617,593 42,020,092 Prior EIB-168 Bts.Cabdin Wajo-Pareman 25-Oct-07 2-Nov-07 25-Oct-07 2-Nov-07 24-Apr-08 5-Jun-08 17-Jul-08 24-Jul-08 3-Oct-08 Nat. Road 365 3-Oct-09 03-60/EIB- 9 Maluku/IU ICB 6,999,977 63,699,788 Prior EIB-169 Kobisonta-Banggoi, etc. 31-Jan-08 12-Feb-08 31-Jan-08 12-Feb-08 26-Feb-08 9-Apr-08 11-Jun-08 18-Jun-08 16-Jul-08 Rp 75,920,243,000 Nat. Road PT Waskita Karya 400 20-Aug-09 169/RB/A/4744/0708 04-60/EIB- 10 Maluku/IU ICB 7,438,196 67,687,583 Prior EIB-170 Banggoi-Bula 31-Jan-07 12-Feb-08 31-Jan-07 12-Feb-08 26-Feb-08 9-Apr-08 11-Jun-08 20-Jun-08 16-Jul-08 Rp 81,150,917,000 Nat. Road PT Adhi Karya, JO 365 16-Jul-09 170/RB/A/4744/0708 Sub-Total Cost 1 : 59,074,037 537,573,738 NCB Prior Review ( USD 1 million) PT. Sinar Sama Sejati, 01-60/EIPB- 1 Maluku/IU NCB 2,787,363 25,365,000 Prior EIPB-143 Besi-Wahai 18-Sep-07 1-Oct-07 18-Sep-07 1-Oct-07 11-Oct-07 27-Nov-07 24-Jan-08 12-Feb-08 21-Feb-08 Rp 28,647,182,000 Nat. Roads 360 15-Feb-09 JO 143/RB/A/4744/0208 2 Kalteng/Prov NCB 2,029,780 18,471,000 Prior EIB-171 Ampah-Buntok 9-Nov-07 21-Nov-07 9-Nov-07 21-Nov-07 25-Feb-08 27-Mar-08 9-Jul-08 18-Jul-08 22-Aug-08 Rp 24,455,467,000 Prov. Roads 365 22-Aug-09 3 Sulteng/Prov NCB 2,447,872 22,275,639 Prior EIB-173 Pape-Tomata 7-Nov-07 16-Nov-07 7-Nov-07 16-Nov-07 5-Dec-07 17-Jan-08 28-Feb-08 6-Mar-08 16-May-08 Prov. Roads 360 11-May-09 PT Angkasapuri 4 Sulteng/Prov NCB 2,218,580 20,189,075 Prior EIP-142 Palupi-Bangga 25-Oct-07 1-Nov-07 25-Oct-07 1-Nov-07 5-Dec-07 17-Jan-08 9-Jul-08 18-Jul-08 17-Aug-08 Rp 17,199,744,000 Prov. Roads 360 12-Aug-09 Konsursindo 5 Sulsel/Prov NCB 1,003,793 9,134,514 Prior EIBR-108 S. Solo Bridge 11-Feb-08 21-Feb-08 11-Feb-08 21-Feb-08 24-Apr-08 11-Jun-08 23-Jul-08 30-Jul-08 9-Oct-08 Prov. Roads 300 5-Aug-09 Pasarwajo-Matanauwe, 6 Sultra/Prov NCB 2,170,104 19,747,945 Prior EIPB-144 14-Nov-07 28-Nov-07 14-Nov-07 28-Nov-07 16-Jun-08 18-Jul-08 29-Aug-08 5-Sep-08 15-Nov-08 Prov. Roads 330 11-Oct-09 etc. 7 Papua/Prov NCB 2,394,092 21,786,234 Prior EIB-174 Kimibay-Napan 18-Apr-08 24-Apr-08 18-Apr-08 24-Apr-08 16-May-08 18-Jun-08 30-Jul-08 6-Aug-08 16-Oct-08 Prov. Roads 300 12-Aug-09 8 Papua/Prov NCB 1,922,900 17,498,393 Prior EIB-190 Waena-Arso V 5-Mar-08 1-Apr-08 5-Mar-08 1-Apr-08 12-May-08 11-Jun-08 23-Jul-08 30-Jul-08 9-Oct-08 Prov. Roads 300 5-Aug-09 9 Kalsel/Kab NCB 1,211,022 11,020,300 Prior EIB-178 Halong-Gunung Riut, etc. 9-Nov-07 21-Nov-07 9-Nov-07 21-Nov-07 12-May-08 16-Jun-08 28-Jul-08 4-Aug-08 14-Oct-08 Balangan 365 14-Oct-09 Timor Tengah 10 NTT/Kab NCB 1,439,903 13,103,120 Prior EIPB-145 Amol-Manamas, etc. 31-Mar-08 18-Apr-08 31-Mar-08 18-Apr-08 25-Jun-08 28-Jul-08 8-Sep-08 15-Sep-08 25-Nov-08 240 23-Jul-09 Utara PT. Harfia Graha P, Karampuang-Hila Hila, 11 Sulsel/Kab NCB 1,214,850 11,055,138 Prior EIB-183 14-Nov-07 27-Nov-08 14-Nov-07 27-Nov-08 24-Dec-07 31-Jan-08 24-Apr-08 4-Jun-08 4-Jul-08 Bulukumba PT Sabar Jaya 365 4-Jul-09 etc. Pratama JO PT Artamakmur 12 Papua/Kab NCB 1,321,025 12,021,330 Prior EIB-189 Korem-Yenggarbun 18-Apr-08 24-Apr-08 18-Apr-08 24-Apr-08 8-May-08 10-Jun-08 31-Jul-08 8-Aug-08 8-Oct-08 Rp 13,648,219,000 Biak Numfor 240 5-Jun-09 Permai 13 Papua/Kab NCB 2,801,900 25,497,287 Prior EIP-143 Kumbe-Salor III 5-Mar-08 1-Apr-08 5-Mar-08 1-Apr-08 15-Apr-08 16-May-08 27-Jun-08 4-Jul-08 13-Sep-08 Merauke 300 10-Jul-09 Sub-Total Cost 2 : 24,963,184 227,164,975 NCB Post Review 2nd Packet... etc Tamiyang Layang- PT Benawa Citra 17.32/EIB- 1 Kalteng/Kab NCB 468,099 4,259,700 Post EIB-176 27-Jul-07 14-Nov-07 27-Jul-07 14-Nov-07 29-Feb-08 1-Apr-08 22-May-08 30-May-08 1-Jul-08 Rp 4,125,371,946.22 Barito Timur 180 28-Dec-08 Katambung Putra Tabalong 176/PM/C/4744/0708 Hulu Sungai 2 Kalsel/Kab NCB 733,725 6,676,900 Post EIB-177 Danau Panggang-Babirik 30-Jul-07 14-Nov-07 30-Jul-07 14-Nov-07 12-Apr-08 29-May-08 26-Jun-08 10-Jul-08 26-Sep-08 265 18-Jun-09 Utara 02-6524/EIB- 3 NTT/Kab NCB 889,230 8,091,996 Post EIB-179 Lelahomi-Mainang 13-Feb-08 19-Feb-08 13-Feb-08 19-Feb-08 5-Mar-08 8-Apr-08 16-May-08 11-Jun-08 4-Jul-08 Rp 9,388,598,000 Alor PT Adhi Karya 300 30-Apr-09 179/RB/C/4744/0708 4 NTT/Kab NCB 912,492 8,303,675 Post EIB-180 Roa-Saga, etc. 7-Aug-07 21-Apr-08 7-Aug-07 21-Apr-08 26-Jun-08 26-Jul-08 23-Aug-08 6-Sep-08 23-Nov-08 Ende 240 21-Jul-09 5 Sulsel/Kab NCB 347,278 3,160,233 Post EIB-184 Cikoang/Laikang-Puntodo 9-Aug-07 29-Oct-07 9-Aug-07 29-Oct-07 16-Jan-08 21-Feb-08 26-Jun-08 9-Jul-08 23-Jul-08 Rp 3,134,933,000 Takalar PT Cisco Sinar Jaya 180 19-Jan-09 PT Citratama T-PT 6 Sulsel/Kab NCB 623,406 5,672,995 Post EIB-185 Batebala-Tarutu Campaga 9-Aug-07 29-Oct-07 9-Aug-07 29-Oct-07 23-Jan-08 26-Feb-08 14-May-08 26-May-08 25-Jun-08 Rp 5,627,367,793 Bantaeng 150 22-Nov-08 Nugraha T, JO 7 Sulsel/Kab NCB 355,328 3,233,486 Post EIB-186 Kaluku-Malaka 5-Oct-07 29-Oct-07 5-Oct-07 29-Oct-07 10-Apr-08 14-May-08 11-Jun-08 25-Jun-08 11-Sep-08 Maros 180 10-Mar-09 8 Sulsel/Kab NCB 241,564 2,198,235 Post EIB-187 Tacipi-Tokaseng 1-Aug-07 29-Oct-07 1-Aug-07 29-Oct-07 23-Jan-08 26-Feb-08 25-Mar-08 8-Apr-08 25-Jun-08 Bone 270 22-Mar-09 Sub-Total Cost 3 : 4,571,123 41,597,221 CP = Construction Period Total Cost : 88,608,344 806,335,933 All Works and Goods Packets apply Post Qualification and Unit Price Contract methods DP = Delivery Period Note Post Review < USD 1 million Prior Review > USD 1 million Date of process already complete Expected date to complete Date overdue For Prior Review Packages : 1. From bid opening to request for World Bank no objection max 6 weeks 2. From bid opening to award max 120 days For Post Review Packages : 1. From bid opening to request for Bina Program approval max 4 weeks 2. From bid opening to award max 120 days Page 2 DEIRTP2 AWP1-2-3 for ProcPlan Aug 08 - actual modified
Groupe de la Banque mondiale · Procurement Plan
Indonesia - Second Eastern Indonesia Region Transport Project (EIRTP-2) : procurement plan
Voir le document original
Le texte intégral est hébergé par l’organisation qui le publie. lawenc.com indexe les métadonnées et renvoie vers la source officielle.
Texte intégral
Informations clés
Organisation
Groupe de la Banque mondiale
Type de document
Procurement Plan
Pays
Indonésie
Source
Banque mondiale