Группа Всемирного банка · Procurement Plan

Vietnam - Red River Delta Rural Water Supply and Sanitation Project : procurement plan for 2008 (18 months) Hai Duong province

Всемирный банк
Открыть оригинал документа

Полный текст размещён на сайте публикующей организации. lawenc.com индексирует метаданные и ведёт на официальный источник.

Полный текст

50430 PROCUREMENT PLAN IN 18 MONTHS - HAI DUONG PPMU No objection delivered by WB on June 23 2008 Revised in August 2009 Quantit Procurement Contract Estimate IDA Invitati y of Bid opening & No Description d costs revie on for package evaluating s Type Method (USD) w bid Sign Start Complete Component 1: Rural water supply and sanitation A infrastructure A.1 Sub-projects Design and construct water supply system in Thai Duong 1 commune HD07 1 CW NCB 406.000 Prior 01/2008 3/2008 - 05/2008 06/2008 06/2008 06/2009 Design and construct intercommune water supply system 2 in Nhan Quyen - Co Bi commune HD08 1 CW NCB 780.000 Prior 01/2008 3/2008 - 5/2008 06/2008 06/2008 09/2009 Contract management and construction supervision in Thai HD14- 3 Duong and Nhan Quyen - Co Bi communes TV 1 Cons CQS 23,500 Post 06/2008 06/2008 06/2008 06/2008 09/2009 Design and construct water supply system in Thai Thinh 4 commune (Kinh Mon district) HD09 1 CW NCB 600,000 Prior 07/2008 8/2008 - 9/2008 10/2008 10/2008 11/2009 Design and construct water supply system in Thang Long 5 commune (Kinh Mon district) HD10 1 CW NCB 680,000 Prior 07/2008 8/2008 - 9/2008 10/2008 10/2008 11/2009 Contract management and construction supervision in HD15- 6 Thang Long and Thai Thinh (Kinh Mon district) TV 1 Cons CQS 24,500 Post 07/2008 8/2008 - 9/2008 10/2008 10/2008 11/2009 Design and construct water supply system in Ngu Phuc 7 commune (Kim Thanh district) HD17 1 CW NCB 700,000 Prior 07/2008 8/2008 - 10/2008 11/2008 11/2008 12/2009 Design and construct water supply system in Kim Xuyen 8 commune (Kim Thanh district) HD18 1 CW NCB 750,000 Prior 07/2008 8/2008 - 10/2008 11/2008 11/2008 12/2009 Contract management and construction supervision in Ngu HD19- 9 Phuc and Kim Xuyen subprojects TV 1 Cons CQS 27,300 Post 08/2008 8/2008 - 10/2008 11/2008 11/2008 12/2009 Design and construct public toilets in 7 communes in stage 10 2 HD13 1 CW NCB 210,000 Prior 07/2008 8/2008 - 10/2008 10/2008 10/2008 08/2009 Contract management and construction supervision for HD16- 11 public toilets in 07 communes - stage2 TV 1 Cons CQS 7,500 Post 07/2008 8/2008 - 10/2008 10/2008 10/2008 08/2009 Design and construct water supply system in Le Loi and 12 Yet Kieu commune (Gia Loc district) HD21 1 CW NCB 1,448,000 Prior 9/2009 10/2009 - 12/20091/2010 01/2010 02/2011 0 Design and construct water supply system in Pham Tran 13 (Gia Loc district) HD22 1 CW NCB 620,500 Prior 9/2009 10/2009 - 12/20091/2010 01/2010 02/2011 0 Quantit Procurement Contract Estimate IDA Invitati y of Bid opening & No Description d costs revie on for package evaluating s Type Method (USD) w bid Sign Start Complete Design and construct water supply system in Quang 14 Nghiep (Tu Ky district) HD23 1 CW NCB 580,600 Prior 11/2009 12/2009 - 2/201002/2010 02/2010 02/2011 Design and construct water supply system in An Thanh 15 and Tu Xuyen (Tu Ky district) HD24 1 CW NCB 02/2010 02/2010 03/2011 1,350,000 Prior 11/2009 12/2009 - 02/2010 Design and construct water supply system in Cam Dong 16 (Cam Giang district) HD25 1 CW NCB 650,000 Prior 12/2009 1/2010-3/2010 3/2010 4/2010 4/2011 Design and construct water supply system in Cam Phuc 17 (Cam Giang district) HD27 1 CW NCB 830,000 Prior 12/2009 1/2010-3/2010 3/2010 4/2010 4/2011 Design and construct public sanitation in 8 communes in 18 stage 3 HD26 1 CW NCB 315,000 02/2010 02/2010 12/2010 Prior 11/2009 12/2009 - 02/2010 Contract management and construction supervision for water supply system in Pham Tran and joint venture of Le HD28- 19 Loi and Yet Kieu (Gia Loc district) TV 1 Cons CQS 41,500 Post 9/2009 11/2009-12/200901/2010 01/2010 02/2011 Contract management and construction supervision for water supply system in Quang Nghiep, joint venture of An HD29- 20 Thanh and Tu Xuyen- Tu Ky district TV 1 Cons CQS 38,000 Post 9/2009 11/2009-12/200901/2010 01/2010 03/2011 Contract management and construction supervision for HD31- 21 water supply system in Cam Giang district TV 1 Cons CQS 27,900 Post 11/2009 1/2010-2/2010 3/2010 04/2010 4-2011 Contract management and construction supervision for HD32- 22 public sanitation s in 08 communes - stage 3 TV 1 Cons CQS 11,000 Post 10/2009 12/2009-1/2010 2/2010 2/2010 12/2010 A 2 Prepare for sub-projects in following years HD20- 1 Stage 4: Prepare for sub-projects in 08 communes TV 1 Cons QCBS 12/2008 12/2008 163,200 Prior 07/2008 10/2008 - 11/2008 12/2009 HD33- 2 Stage 5: Prepare for sub-projects in 5 communes TV 1 Cons QCBS 120 000 Prior 10/2009 1/2010-3/2010 4/2010 4/2010 4/2011 D Component 4: Support for project management HD04D - 1 Office equipment procurement TB 1 G SP 1,465 Post 06/2008 07/2008 07/2008 07/2008 07/2008 HD11- 2 Vehicle procurement HH 1 G SP 33,000 Post 07/2008 07/2008 08/2008 08/2008 09/2008 Technical supports for PPMU on technical and HD12- 3 procurement management TV Cons CQS 18,000 Post 11/2009 12/2009 01/2010 01/2010 06/2010 Quantit Procurement Contract Estimate IDA Invitati y of Bid opening & No Description d costs revie on for package evaluating s Type Method (USD) w bid Sign Start Complete Note * Package No: HD25 and HD27 seperated from HD25 in the 18 months of procurement plans, received no objection by WB on 23/6/2008 HD28-TV is combined by 02 packages HD27-TV and HD28-TV in the 18 months of procurement plans, received no objection by WB on 23/6/2008 HD29-TV is combined by 02 packages HD29-TV and HD30-TV in the 18 months of procurement plans, received no objection by WB on 23/6/2008 * Revised implementation time for packages No: HD21; HD22; HD23; HD24; HD25; HD26; HD27; HD28-TV, HD29-TV; HD31-TV; HD32-TV; HD33-TV;

Основные сведения
Тип документа Procurement Plan
Дата принятия
Источник Всемирный банк