World Bank Group · Procurement Plan

Bangladesh - Enterprise Growth and Bank Modernization Project : procurement plan for Bangladesh Export processing Zones Authority (BEPZA)

Bangladesh World Bank
View original document

The full text is hosted by the publishing organisation. lawenc.com indexes the metadata and links to the official source.

Full text

/ , 55137 Procurement Planning And Monitoring Format Name of Project: Enterprise Growth And Bank Modernization Project(IDA Credit No. 3917-BD) (1 US$ = BOT 69.00) Sub Project: Refurbishing Assets of Chittagong Steel Mills And Adamjee Jute Mills for Converting into EPZs Implementing Agency: Bangladesh Export processing Zones Authority (BEPZA) Credit Effective Date: July 19, 2004 Credit Closing Date: November 30, 2009 Revised as on 26.04.2009 Planned date Progress Estimated Cost Planned date Name of Contract Prior of delivery of Name of the Contract Quantityl (in US$) Procedure of contract Supplierl SI package Review I completion procurment Remarks (Brief Description) Number Contract Price Imethod signing and Contractorl no (Yes/No) and as on with currency actual date Consultant actual date today 1 2 3 4 5 6 7 8 9 10 11 12 Refurbishing Assets of Chittagong Steel Mills for converting into EPZ As per decision of government the existing old unusable structures is Dismantling & partial Tk.50,000.00 being demolished through 1 W-1 Refurbishment works NCB No Jul2009 Dec 2009 (us$ 724.64) international auction. However some (North) demolishl site cleaning may require at final staQe. Tk. 9,34,20,794.57 (us$ 13,53,924.56) Refurbishment of Contract amount: AWCPL& 2 W-3 8800 sqm NCB Yes 17-Aug-06 30-Aug-08 100% Completed. Factory Building-1 Tk. 9,03,48,259.91 FAEL JV Revised amount Tk. 82 421 864.84 Tk. 9,44,17,212.47 (us$13,68,365.40) Refurbishment of Contract amount: Mis. Taher 3 W-4 8800 sqm NCB Yes 17-Aug-06 30-Aug-08 100% Completed. Factory Building-2 Tk.8,91,80,936.74 Brothers Ltd I Revised amount Tk. 791 83315.38 Tk.12,79,99,163.90 Refurbishment of (us$18,55,060.35) Mis. Samsuddin 4 W-5 8800 sqm NCB Yes Jan 2008 30-0ct-09 37% Construction is ongoing. I Factory Building-3 Contract amount: Ahmed & Co. Ltd Tk.11,28,88,655.79 3rd RDPP 11 mar 09 , ~ Procurement Planning And Monitoring Format Name of Project: Enterprise Growth And Bank Modernization Project(IDA Credit No. 3917-BD) (1 US$ = BOT 69.00) Sub Project: Refurbishing Assets of Chittagong Steel Mills And Adamjee Jute Mills for Converting into EPZs Implementing Agency: Bangladesh Export processing Zones Authority (BEPZA) Credit Effective Date: July 19, 2004 Credit Closing Date: November 30, 2009 Revised as on 26.04.2009 Planned date Progress Estimated Cost Planned date Name of Contract Prior of delivery of Name of the Contract Quantityl (in US$) Procedure of contract Supplierl SI package Review I completion procurment Remarks (Brief Description) Number Contract Price Imethod signing and Contractorl no (Yes/No) and as on with currency actual date Consultant actual date today 1 2 3 4 5 6 7 8 9 10 11 12 Tk.4,25,80,797.01 NOC for draft bidding document has Renovation of Existing (us$ 6,17,113.00) 5 W-6 41115 sqm NCB Yes Jul2009 Jun 2010 been obtained and tendering Road Recast amount: process is ongoing. Tk. 44875057.00 Tk.5,29,40,000.00 Re-Excavation of existing NOC for draft bidding document has (us$7,67,246.38) 6 W-7 canal and Renovation of 7078 m NCB Yes Jul2009 Jun 2010 been obtained and tendering Recast amount: drainage system process is ongoing. Tk. 50837511.48 Tk.1,65,45,192.04 (us$2,39,785.39) Strengthening of MIs. M.N Alam 3026 m, Contract amount: 7 W-8 boundary wall and Sentry NCB No Nov 2006 Mar 2008 Brothers - Asha 100% Completed. 25 sqm Tk.1 ,45,46,095.71 post Construction Revised amount: 1 1891 491.77 Tk.84,99,518.16 Renovation of Existing (us$ 1,23,181.42) M/s.Prime Work is suspended due to 8 W-10 5710 m NCB No Jan 2008 Jun 2009 75% water supply system Contract amount: construction. unavailability of workable site. Tk.8673190.54 Upgradaton and Tk.1,15,57,824.90 installation of 11 1.415 11 no, (us$1,67,504.70) Energypac 9 W-12 NCB No Feb 2007 Apr 2009 100% Completed. KV SUb-Station and 4100 m Contract price: Engineering Ltd 11 kv high tension line Tk.1 14 48 645.00 3rd RDPP 11 mar 09 2 Procurement Planning And Monitoring Format Name of Project: Enterprise Growth And Bank Modernization Project(IDA Credit No. 3917-BD) (1 US$ = BOT 69.00) Sub Project: Refurbishing Assets of Chittagong Steel Mills And Adamjee Jute Mills for Converting into EPZs Implementing Agency: Bangladesh Export processing Zones Authority (BEPZA) Credit Effective Date: July 19, 2004 Credit Closing Date: November 30, 2009 Revised as on 26.04.2009 Planned date Progress Estimated Cost Planned date Name of Contract Prior of delivery of Name of the Contract Quantity/ (in US$) Procedure of contract Supplier/ SI package Review / completion procurment Remarks (Brief Description) Number Contract Price /method signing and Contractor/ no (Yes/No) and as on with currency actual date Consultant actual date today 1 2 3 4 5 6 7 8 9 10 11 12 Up gradation of Gas Tk.6,75,360.00 Comencement of work is waiting Supply System: (us$9,787.83) M/s.R.M. 10 W-28 4500 m NCB No Apr 2008 Jun 2009 upto obtaining completion material Installation of Gas Supply Contract price: construction from BGSL. Line i/c related works. Tk.6,61 ,202.00 Up gradation of Gas Supply System at Tk.1 ,00,19,385.05 The work has to be done through Kamaphuli EPZ: (us$1,45,208.48) 11 W-31 4500 m FA Yes Nov 2008 Jun 2009 BGSL by deposit work. Deposit Procurement of special Contract amount: payment to BGSL is under process. quality materials for Gas Tk.1,13,75,439.00 Supply system Tk.48,70,963.07 Upgradation of (us$ 70,593.67) Work is suspended due to 12 W-32 4000 m NCB No Jan 2008 Jun 2009 38% Street Light Contract amount: unavailability of workable site. Tk.43 60 331.29 M/s.Modhu Traders Tk. 53,09,480.07 Upgradation of (us$ 76,948.99) Work is suspended due to 13 W-33 2970 m Jan 2008 Jun 2009 57% Security light Contract amount: unavailability of workable site. Tk. 47 31 286.09 3rd RDPP 11 mar 09 3 : Procurement Planning And Monitoring Format Name of Project: Enterprise Growth And Bank Modernization Project(IOA Credit No. 3917-BO) (1 US$ = BOT 69.00) Sub Project: Refurbishing Assets of Chittagong Steel Mills And Adamjee Jute Mills for Converting into EPZs Implementing Agency: Bangladesh Export processing Zones Authority (BEPZA) Credit Effective Date: July 19, 2004 Credit Closing Date: November 30, 2009 Revised as on 26.04.2009 Planned date Progress Estimated Cost Planned date Name of Contract Prior of delivery of Name of the Contract Quantity/ (in US$) Procedure of contract Supplier/ SI package Review / completion procurment Remarks (Brief Description) Number Contract Price /method signing and Contractor/ no (Yes/No) and as on with currency actual date Consultant actual date today I 1 2 3 4 5 6 7 8 9 10 11 12 Newly proposed works for KEPZ I There is an old boundary wall at the I Construction of boundary west which needs to be dismantled wall of sector-02, KEPZ, Tk. 1,57,76,255.00 14 W-37 929 rm NCB No Jul2009 Jun 2010 and to buil a new boundary wall as North Pantenga. (US$ 228,641.37) per SOP which are away from the I Chittagong (Group-Ka) I existing boundary wall. Construction of boundary wall at the South-east of There is about 6'-0"high boundary Tk.1,96,26,656.00 15 W-38 sector-01, KEPZ, North 1294.11rm NCB No Jul2009 Jun 2010 wall which needs to be dismantled & (US$ 284,444.28) Pantenga, Ctg. (Group- rebuild as per SOP of BEPZA. Khal Construction of boundary There is an old boundary wall which wall at the South-east of Tk. 35,01,179.56 needs to be dismantled and to 16 W-39 sector-01, KEPZ, North 268.29 rm NCB No Jul2009 Jun 2010 (US$ 50,741.73) rebuild a new boundary wall near to Pantenga. Ctg (Group- the boundary wall as per SOP. Gal 3rd RDPP 11 mar 09 4 : Procurement Planning And Monitoring Format Name of Project: Enterprise Growth And Bank Modernization Project(lDA Credit No. 3917.BD) (1 US$ = BOT 69.00) Sub Project: Refurbishing Assets of Chittagong Steel Mills And Adamjee Jute Mills for Converting into EPZs Implementing Agency: Bangladesh Export processing Zones Authority (BEPZA) Credit Effective Date: July 19, 2004 Credit Closing Date: November 30, 2009 Revised as on 26.04.2009 Planned date Progress Estimated Cost Planned date Name of Contract Prior of delivery of Name of the Contract Quantityl (in US$) Procedure of contract Supplierl SI package Review I completion procurment Remarks (Brief Description) Number Contract Price Imethod signing and Contractorl no (Yes/No) and as on with currency actual date Consultant actual date today 1 2 3 4 5 6 7 8 9 10 11 12 Refurbishin~Assets of Adamjee Jute Mills for converting into EPZ Tk.13,41,84,640.05 (us$19,44,704.93) Problems are: Refurbishment of Contract amount: MIs. The United 1. Site Icoation changed 17 W-16 8800 sqm NCB Yes Dec 2007 Dec 2009 30% factory building-1 Tk.12,41 ,68, 195.67 Construction Ltd. 2. Soil tested Revised amount: 3. Design revetting by BUET 123623752.00 Tk.13,41,84,640.05 (us$19,44,704.92) Problems are: Refurbishment of Contract amount: MIs. The United 1. Site Icoation changed 18 W-17 8800 sqm NCB Yes Dec 2007 Aug 2009 55% factory building-2 Tk.12,41 ,68, 195.67 Construction Lte 2. Soil tested Revised amount: 3. Design revetting by BUET 121982629.00 Tk.8,93,42, 733.74 Problems are: (us$ 12,94,822.23) 1. Geneva camp has not yet Renovation of Contract amount: MIS. PTSL- 19 W-19 50835 sqm NCB Yes Dec 2007 Jun 2009 40% removed Existing Road Tk.8,70,33,905.36 STCJV 2. BJMC old structures are not yet Revised amount: fully removed lt49,55,07 4~94 - - - - - - - - - - - 3rd RDPP 11 mar 09 5 : Procurement Planning And Monitoring Format Name of Project: Enterprise Growth And Bank Modernization Project(IDA Credit No. 3917-BD) (1 US$ = BOT 69.00) Sub Project: Refurbishing Assets of Chittagong Steel Mills And Adamjee Jute Mills for Converting into EPZs Implementing Agency: Bangladesh Export processing Zones Authority (BEPZA) Credit Effective Date: July 19, 2004 Credit Closing Date: November 30, 2009 Revised as on 26.04.2009 Planned date Progress Estimated Cost Planned date Name of Contract Prior of delivery of Name of the Contract Quantityl (in US$) Procedure of contract Supplierl SI package Review I completion procurment Remarks (Brief Description) Number Contract Price Imethod signing and Contractorl no (Yes/No) and as on with currency actual date Consultant actual date todav 1 2 3 4 5 6 7 8 9 10 11 12 Work is going on. Tk.2,19,72,313.55 Problems are: (us$318,439.33) 1. Geneva camp has not yet Repair & Renovation of Contract amount: MIS Mitali 20 W-20 6660 m NCB No Dec 2006 Jul 2009 39% removed existing Drain Tk.2,58,21,000.00 Enterprise 2. BJMC old structures are not yet Revised amount: fully removed 2,58,21,399.14 3. Shortaae of MS Rod. Work is going on. Tk. 1,30,80,541.65 Problems are: Convertion of Existing (us$ 1,89,573.07) 1. Geneva camp has not yet boundary wall to 1872 m, Contract amount: MIS Bhuban Kabir removed 21 W-21 NCB No Apr 2007 Nov 2009 60% custom fance and 10 nos Tk.1 ,52,28,110.61 Consurtium 2. BJMC old structures are not yet Security boxes Revised amount: fully removed 1,26,66,343.61 3. PDB power plant drain outlet not Ivet comoleted Renovation of existing The work was stopped since 10-May Over head water tank, 3No, Tk.1,63,38,062.75 08 because the rest of the site is not water supply system i/c 7150 m, (us$ 2,36,783.52) Md.Khairul 22 W-22 NCB No Apr 2007 Jun 2009 75% workable now due to existence of pumphouse, deep 1 no, Contract amount: Kabir Rana Sumilpara Geneva camp. Balance tube well, surface 30 Acrs Tk.1,50,47,041.45 time required is 60 days. water tank (Pond) 3rd RDPP 11 mar 09 6 : Procurement Planning And Monitoring Format Name of Project: Enterprise Growth And Bank Modernization Project(IDA Credit No. 3917-BD) (1 US$ = BOT 69.00) Sub Project: Refurbishing Assets of Chittagong Steel Mills And Adamjee Jute Mills for Converting into EPZs Implementing Agency: Bangladesh Export processing Zones Authority (BEPZA) Credit Effective Date: July 19, 2004 Credit Closing Date: November 30, 2009 Revised as on 26.04.2009 Planned date Progress I Estimated Cost Planned date Name of Contract Prior of delivery of Name of the Contract Quantityl (in US$) Procedure of contract Supplierl I SI package Review I completion procurment Remarks (Brief Description) Number Contract Price Imethod signing and Contractorl no (Yes/No) and as on I with currency actual date Consultant actual date today 1 2 3 4 5 6 7 8 9 10 11 12 I Tk.,1,22,75,981.50 Work is suspended now due to non Upgradaton and (us$1,77,912.77) availability of site for the existence of l installation of 11/.415 Kv 11 no, Contract price: MIs. Subecha old structures of BJMC. Remaining 23 W-26 NCB No Mar 2007 Jun 2009 65% Sub-Station and 11 Kv 3900 m Tk.,1 ,20,16,900.00 Engineering work will be completed within next high tension line Revised amount: 18 days after availability of balance 11013320.00 site. Tk.1,15,02,454.00 Due to unavailability of workable site Upgradation of Street (us$166,702.23) M/s.A.S. 24 W-27 48720 m NCB No Aug 2007 Jun 2009 40% the work was suspended from 15- Light & Security light Contract amount Corporation Oct-08. Tk. 9896864.19 Renovation of existing Gas Supply System: Work is suspended until obtaining Tk.14,62,497.00 25 W-29 Installation of Gas 4500 m NCB No Nov 2008 Oct 2009 MIs. Gasoil Liners - necessary material from Bakhrabad (us$21,195.61) Supply Line i/c Gas Systems Ltd. related works. Tk.49,48,836.98 (us$71,722.28) Renovation of Guest Contract price: MIS Foresight 26 W-30 1385 sqm NCB No Mar 2007 Feb 2008 100% Completed house, GM Banglo Tk.37,10,000.00 Builders Revised amount: 41.98.184.26 - 3rd RDPP 11 mar 09 7 f

Key facts
Organisation World Bank Group
Document type Procurement Plan
Adoption date
Country Bangladesh
Source World Bank